Key Highlights

  • The deposit lies about 10 kilometres west of the flagship Tabba Tabba project in Western Australia's Pilbara.
  • The study is based on a probable ore reserve of 48.3 million tonnes at 0.97 per cent lithium oxide, mainly from the Leia open pit.
  • According to its ASX announcement of 23 November 2026, Wildcat has defined a maiden Inferred resource at Bolt Cutter Central of 14.8 million tonnes at 1.0 per cent lithium oxide, using a 0.7 per cent cut-off.
  • Pre-production Capital is estimated at A$774 million, with a payback of 3.8 years.

Wildcat Resources Ltd (ASX:WC8) is developing lithium projects in Western Australia's Pilbara region. The maiden Bolt Cutter Central resource adds to the mineral inventory being assessed alongside its Tabba Tabba development plans. The company’s shares were trading at AUD 0.20 at 3:45 PM AEDT on 26 November 2026, up 5.41% for the session.

Market backdrop on Thursday

Resources shares rebounded across the market on 26 November after falling on Wednesday. A mid-morning market report noted that the materials sector rose about 2 per cent at the open and that lithium producer PLS Group was among the leading gainers, though no lithium-specific catalyst was identified. A broader recovery in battery-metal stocks is a plausible backdrop for Wildcat's rise, but that link is not established.

The lithium price picture is mixed.

The Bolt Cutter Central resource

According to its ASX announcement of 23 November 2026, Wildcat has defined a maiden Inferred resource at Bolt Cutter Central of 14.8 million tonnes at 1.0 per cent lithium oxide, using a 0.7 per cent cut-off. That equates to roughly 148,000 tonnes of contained lithium oxide. At a lower 0.6 per cent cut-off, the estimate rises to 20.4 million tonnes at 0.9 per cent.

The deposit lies about 10 kilometres west of the flagship Tabba Tabba project in Western Australia's Pilbara. About 90 per cent of the resource sits within 160 metres of surface, and the company is considering open-pit mining. Earlier testwork on three drill-core samples averaged 82.5 per cent recovery and a 5.66 per cent lithium oxide concentrate.

Bolt Cutter is not included in Wildcat's ore reserve or production plans.

Tabba Tabba feasibility figures

Pre-production capital is estimated at A$774 million, with a payback of 3.8 years.

The study is based on a probable ore reserve of 48.3 million tonnes at 0.97 per cent lithium oxide, mainly from the Leia open pit. Output is planned to ramp up to 600,000 tonnes a year of spodumene concentrate by year three. Wildcat reported cash of A$76.1 million at 30 September 2026.

Risks to weigh

The new resource is entirely Inferred, the lowest-confidence category, and metallurgical results so far come from small-scale tests. Raising capital on the scale needed for Tabba Tabba would depend on lithium prices, which have been volatile. The board is also in transition, with an interim chair appointed on 9 November 2026.

What comes next

Wildcat plans to assess Bolt Cutter Central as supplementary feed for a Tabba Tabba plant. Work includes a scoping study, environmental baseline surveys, further metallurgy and a Mining Lease application. At Tabba Tabba, detailed design and engineering are under way ahead of a final Investment decision, for which no date has been given.