Key Highlights
- Its July 2025 updated pre-feasibility study set out a 1.2 million tonne a year carbon-in-leach processing plant.
- Processing was paused at the company's request on 31 August 2026 and resumed on 14 September.
- The company has offered a further $10 million to fund a predator-proof sanctuary.
- Spot gold had fallen sharply during the US session on 25 November.
Santana Minerals Ltd (ASX:SMI) is advancing the Bendigo-Ophir gold project in New Zealand. Project studies and environmental consent requirements remain central to the development pathway. The company’s shares were trading at AUD 0.52 at 3:35 PM AEDT on 26 November 2026, up 10.64% for the session.
A broad rebound across gold miners
The rise came on a day when many ASX gold stocks climbed together.
Spot gold had fallen sharply during the US session on 25 November. That sector backdrop is a possible explanation for Santana's move, but it is not confirmed.
The Bendigo-Ophir project
Santana is listed on both the ASX and the NZX. Its main asset is the Bendigo-Ophir Gold Project in Central Otago, New Zealand, which centres on the Rise and Shine deposit.
Its July 2025 updated pre-feasibility study set out a 1.2 million tonne a year carbon-in-leach processing plant. It assumed peak annual output of around 120,000 ounces and an initial mine life of 14 years.
Drilling keeps returning high grades
Hole MDD537 returned 26.9 metres at 13.0 grams per tonne gold from 152.3 metres. MDD536 returned 34.4 metres at 8.8 g/t, and MDD528 returned 24.4 metres at 10.9 g/t.
The programme also hit a deeper high-grade zone below the main HG1 domain, including 2.0 metres at 89.5 g/t in MDD528. The results are still being assessed before they go into resource modelling and mine planning.
Consent is the key hurdle
Santana is seeking consent under New Zealand's fast-track approvals regime.
The process has been slow. Processing was paused at the company's request on 31 August 2026 and resumed on 14 September. The September quarter report expected a draft decision in November or December 2026.
The panel has focused on lizards. The Department of Conservation has opposed the project on those grounds. The company has offered a further $10 million to fund a predator-proof sanctuary.
Funding and risks
That followed an A$130 million Placement completed earlier in 2026.
The main risks are a refused consent, or one with costly conditions, and further delays that push back first gold. The project also still needs financing and a final Investment decision. And with no Revenue yet, the share price remains exposed to swings in the gold price.
The next confirmed milestone is the fast-track panel's final decision, scheduled for 20 January 2027.