Highlights
- True North Copper (ASX:TNC) released pre-feasibility study metrics for its Cloncurry Copper Project in Queensland.
- The base case reports a post-tax NPV8 of A$123 million and an IRR of 108%.
- Pre-production Capital is only about A$8 million, with peak funding of about A$53 million.
- Payback is 10 months in the base case, or 8 months at spot Commodity prices.
- The study has an accuracy range of ±25%, and a final Investment decision is not expected until late 2027.
True North Copper Limited (ASX:TNC) is advancing the Cloncurry Copper Project near Mount Isa in north-west Queensland, a group of open-pit copper-gold deposits that includes Great Australia, Orphan Shear, Taipan and Wallace North. The company released the results of a pre-feasibility study that reflects a staged restart using existing infrastructure and Glencore arrangements. The study sets out expected economics, funding needs and the timetable to a final investment decision.
Study Economics
The base case assumes a copper price of US$5.90 per pound, a gold price of US$4,200 per ounce and an Exchange Rate of 70 US cents. On those inputs the study reports a post-tax NPV8 of A$123 million, an internal rate of return of 108% and EBITDA of A$220 million. All-In Sustaining Cost is about A$5.09 per pound. True North Copper (ASX:TNC) reports payback of 10 months, or 8 months at spot prices. The study has an accuracy range of plus or minus 25%, so the figures are estimates rather than commitments.
Capital and Funding
Pre-production capital is estimated at about A$8 million, reflecting the use of existing processing arrangements rather than a new plant. Peak funding, which accounts for Working Capital and early-stage costs, is about A$53 million. The project also benefits from carried-forward tax losses of about A$206 million. True North Copper (ASX:TNC) has existing Debt funding from Nebari and will need to establish how the remaining requirement is met. The low capital intensity is the main attraction of the study.
Offtake and Processing
Glencore buys the copper concentrate under a binding offtake and toll-treatment arrangement, which provides a defined route to market. Kanins is expected to purchase copper sulphate. Earlier studies evaluated toll treatment of sulphide ore at nearby facilities including Mount Isa, Ernest Henry and Rocklands. The company has also published a scoping study for the Wynberg gold-copper deposit, which showed a production target of 0.87 million tonnes containing 53,000 ounces of gold equivalent and pre-tax Cash Flow of A$53 million to A$87 million.
Timeline and Risks
The study points to a final investment decision between late 2027 and early 2028, with Mining at Wallace North from the second half of 2028. Key risks include commodity and currency movements, regulatory approvals, mining dilution and the accuracy range of a pre-feasibility study. True North Copper (ASX:TNC) also plans resource and reserve work at Wallace North, where drilling has identified extensions beyond the current pit limits, and continued exploration at its Mt Oxide tenements.
Key Insights
The pre-feasibility study positions True North Copper (ASX:TNC) as a low-capital restart that relies on existing processing and Glencore offtake, with strong modelled returns at the assumed commodity prices. The ±25% accuracy range, the long lead time to a decision and the need for funding mean the figures should be treated as study estimates.