Key highlights

  • Yangibana’s revised Stage 1 feasibility study modelled a 19-year mine life and AUD 333.4 million in initial Capital on a 100% project basis.
  • Hastings’ participating interest in the Western Australian Yangibana joint venture is 40%, with Wyloo holding the other 60%.
  • Hastings completed the Acquisition of 49% of the company that owns the Kabin Buri rare earth processing plant on 27 October.

Hastings Technology Metals (ASX:HAS) shares were down 10.81% at AUD 0.165 during the Trading session on 23 November 2026. The S&P/ASX 200 benchmark was at 8,604.70 at 11:29 am AEDT. The rare earths developer holds interests in the Yangibana project in Western Australia and in a processing plant in Thailand. Its 30 October 2026 Quarterly Report summarised the revised Yangibana feasibility study and progress at Kabin Buri.

The revised study sets out a 19-year mine plan

Hastings’ 30 October 2026 report reviewed the updated Stage 1 definitive feasibility study, released in July. The plan involves open-pit Mining and a beneficiation plant producing mixed rare earth concentrate at 27% total rare earth oxides. The study models a 19-year mine life, drawing entirely on a proved and probable ore reserve of 20.93 million tonnes at 0.90% total rare earth oxides. Peak annual concentrate production is modelled at 37,000 tonnes.

The study estimates initial Stage 1 capital of AUD 333.4 million on a project basis, including AUD 32.4 million for growth and contingency. It reports a pre-tax, ungeared net present value of AUD 649 million at an 8% discount rate and an internal rate of return of 34%. The model estimates 2.4 years of payback from first production. Those figures describe the whole project, in which Hastings’ interest is 40%.

The study modelled average annual EBITDA of AUD 108 million after royalties. Its concentrate production case uses an owner-operator mining model and reflects infrastructure already built at the site. The study uses an estimated 85.7% recovery of total rare earth oxides through flotation.

Kabin Buri acquisition completed after quarter end

Hastings completed the purchase of 49% of plant owner BZNM on 27 October. The planned initial plant capacity is approximately 10,000 tonnes per year of monazite concentrate feed and 12,000 tonnes per year of mixed rare earth chloride output. The company plans to incorporate the larger capacity into the initial plant. Upgrade work included tank welding and fabrication and delivery of process vessels, with AUD 1.10 million paid for operational readiness during the quarter.

The transaction terms capped the total consideration for the 49% interest at USD 15 million. The report identified Kabin Buri as the company’s main operating focus for the quarter.

Concentrate and chloride sit at different processing stages

Yangibana is approximately 250 kilometres northeast of Carnarvon in Western Australia’s Gascoyne region. Its feasibility study models a concentrate produced at the mine’s beneficiation plant. At Kabin Buri, Hastings is advancing a hydrometallurgical Facility designed to take monazite concentrate and produce mixed rare earth chloride. The Thailand feedstock framework with Enuo covers a minimum annual Volume of 10,000 tonnes of African-sourced monazite concentrate. The two developments have separate capacity assumptions and operating schedules.

Risks investors are watching

Yangibana’s project-level study results depend on assumptions including a neodymium-praseodymium oxide price of USD 110 per kilogram and an AUD/USD Exchange Rate of 0.70. Hastings described study capital cost accuracy as plus or minus 15%. Financing remains a step towards a final Investment decision, and Wyloo is conducting a sale process for its interest. At Kabin Buri, commencement of production depends on installation, testing, commissioning and arrangements for ramp-up feedstock.

From upgrades to commissioning

In the December quarter, Hastings planned to progress remaining installation and upgrade work at Kabin Buri ahead of testing. The target for first mixed rare earth chloride production was the second quarter of calendar 2027. Hastings was also progressing its application for Thai investment promotion and negotiating to increase its BZNM interest to at least 51%. The company scheduled its AGM for 27 November 2026.

Funding and readiness will mark the next phase

The Yangibana study defines a Stage 1 mine and plant configuration with Hastings’ share of initial capital estimated at about AUD 133 million. The company’s work in Thailand has moved from a proposed acquisition to a completed 49% interest, with upgrades still under way. Funding at Yangibana and commissioning at Kabin Buri are the next milestones within those separate schedules.