Key Highlights

  • Southern Palladium (ASX:SPD) released an updated pre-feasibility study for Bengwenyama in October 2026.
  • The South African project is designed for staged development, with chrome concentrate as a co-product.
  • The revised study forecasts a peak funding requirement of US$329 million on a whole-project basis.
  • South Africa granted a Mining right for an initial 30 years in August.

Southern Palladium (ASX:SPD) is advancing definitive feasibility work for Bengwenyama after updating the project’s pre-feasibility study in October 2026. The developer holds a 70% indirect interest in the South African platinum group metals and chrome project, with the remaining interest held by the Bengwenyama Traditional Council through the project company.

Mine plan and chrome contribution

The study sets out a staged development of the deposit in the Bushveld Complex. The plan draws on the UG2 reef for its Probable Ore Reserve, reported at 6.29 million ounces on a six-element basis. The company’s wider combined Mineral Resource covers the UG2 and Merensky reefs and uses different reporting bases for the two reefs.

Chrome concentrate is planned as a co-product. The updated study forecasts annual output of about 450,000 tonnes at Stage 1 and around one million tonnes once Stage 2 reaches steady state. The extra production would make chrome a larger contributor to projected Revenue alongside platinum group metals.

Study Economics and funding requirements

The October study forecast peak funding of US$329 million, compared with US$279 million in the prior optimised study. Both figures reflect the entire project. The increase in required funding sits alongside a higher forecast post-tax net present value in the revised study.

Project economics will depend on prices for the individual metals in the basket, chrome sales, metallurgical recoveries and operating costs. The feasibility programme will give Southern Palladium a basis for refining those inputs and for assessing how to finance the development.

Mining right and early work

South Africa granted the Bengwenyama mining right in August 2026 for an initial 30 years. The company’s quarterly update identified outstanding waste and water-use approvals as conditions for planned early works. The definitive feasibility study and permitting programme therefore continue alongside the granted mining right.

The October funding and approvals picture

Southern Palladium reported A$20.06 million in cash at 30 September 2026, excluding A$1.13 million held by the project subsidiary. The Quarterly Report identifies definitive feasibility work and preparations for early works as near-term activities. The funding needed for the full mine development is materially larger than these current work programmes.

The company’s study compares a two-stage configuration with its earlier optimised design. Staging the build affects when output and associated revenue would rise. It also means the schedule for the larger second stage depends on progress through the initial phase and on funding for the expansion.