Key highlights

  • Carnavale’s Kookynie feasibility study modelled 18 months of open-pit Mining at the Swiftsure and Tiptoe deposits.
  • The study outlined open-pit reserves of approximately 220,000 tonnes at 5.0 grams per tonne gold, containing about 35,600 ounces.
  • Metallurgical testwork reported gold recoveries of 98% to 99% at a grind size of 106 microns.

Carnavale Resources (ASX:CAV) shares were down 11.86% at AUD 0.052 during the Trading session on 23 November 2026. The S&P/ASX 200 benchmark was at 8,604.70 at 11:29 am AEDT. The gold explorer and developer is advancing the Kookynie Gold Project north of Kalgoorlie. Its 29 October 2026 Quarterly Report covered the open-pit feasibility study, metallurgy and applications for operating approvals.

Kookynie feasibility focuses on two open pits

Carnavale’s 29 October 2026 report summarised a bankable feasibility study released on 26 October. The study outlines mining at Swiftsure and Tiptoe, with about 220,000 tonnes at 5.0 grams per tonne gold for 35,600 ounces in the open-pit reserve. The model assumes an 18-month open-pit operation, contract mining and an ore purchase agreement. The broader project mineral resource is 855,000 tonnes at 4.4 grams per tonne for about 120,000 ounces.

At the study’s base case gold price of AUD 6,000 per ounce, Carnavale estimated undiscounted pre-tax free Cash Flow of AUD 104 million. It reported a pre-tax net present value of AUD 87 million at an 8% discount rate, an internal rate of return of 417% and a maximum Capital drawdown of AUD 24 million. Payback was projected at month ten of operations.

The base case also estimated all-in sustaining costs of AUD 2,721 per ounce for the open-pit operation. The 18-month model covers the two pits as a distinct stage and assumes the project sells ore under an agreement instead of building its own plant.

Testwork and infrastructure drilling

Metallurgical testing reported recovery of 98% to 99% at a grind size of 106 microns. Carnavale also began drilling programmes to investigate exploration targets and proposed infrastructure areas. One comprises more than 4,000 metres at the greenstone and granite boundary, about two kilometres northwest of Swiftsure. A separate programme of more than 3,000 metres is designed to check whether gold mineralisation is present where infrastructure is planned for the open pits.

A proposed staged development in the Goldfields

The project lies about 60 kilometres south of Leonora and 180 kilometres north of Kalgoorlie. The feasibility study addresses open-pit development, while a separate scoping study addresses potential underground mining. Carnavale updated the underground financial assumptions using factors from the feasibility study while keeping its underground resource model unchanged. The underground production target in the updated scoping work was about 47,000 ounces.

The revised pit design leaves about 11,000 ounces of high-grade resources beneath the proposed Swiftsure pit outside its development case. The company intends to evaluate those ounces as part of later underground planning. The concept involves beginning with the two shallow pits before a potential transition to underground mining.

The updated underground case reported potential pre-tax free cash flow of AUD 111 million and all-in sustaining costs of AUD 2,875 per ounce at the same gold price assumption. Those are outputs from the scoping model for the proposed later stage.

Risks investors are watching

The feasibility figures depend on assumptions including the gold price, mine plan, grade, costs and execution schedule. The underground case is at scoping study level, with Carnavale citing an accuracy range of plus or minus 35% and no underground reserve determination from that early work. Project financing, approvals and a final Investment decision remain separate requirements before development.

Permits, financing and the schedule ahead

Carnavale submitted a mining development and closure proposal, a native vegetation clearing permit application and a works approval application. It expected the relevant approvals in the first half of 2027 and intends to complete project Debt Financing and pre-development activities before a final investment decision. It targeted production for the second half of 2027. The schedule remains subject to those preceding steps.

The company plans to use the site drilling data to assess proposed infrastructure locations before development.

The open pits have the more advanced study

Kookynie’s October report sets out a feasibility model for Swiftsure and Tiptoe and a separate concept for later underground work. The near-term tasks cover obtaining approvals, project financing and a development decision. Site and exploration drilling continue alongside those corporate and regulatory steps.