Key highlights
- Liontown reported record underground development of 4,021 metres in the September 2026 quarter, up 21% on the June quarter, in a report dated 29 October 2026.
- Spodumene concentrate production was 77,982 dmt, with 82,561 dmt sold at an average grade of 5.2% Li2O.
- The Kathleen Valley expansion was approved, with a targeted five-year average of about 780,000 dmt a year from FY30.
- Cash at bank was $502 million at quarter end, and the company announced a staged farm-in to the Centenario lithium brine project in Argentina.
Liontown Resources (ASX:LTR) released its Quarterly Activities Report for the period ended 30 September 2026 on 29 October 2026. The report covered the ramp-up of the underground mine at Kathleen Valley, the approval of an expansion at the operation and an initial entry into lithium brine through a farm-in in Argentina.
Operating and Financial Performance
Cash receipts from customers were $193 million. Underlying Operating Cash Flow was $69 million, and a one-off customer settlement payment resulted in operating cash flow of $47 million for the quarter. The settlement related to a confidential dispute over an FY26 shipment, for which a $21.6 million accrual was recognised in the previous year. Capital Expenditure was $82 million, including a $7 million upfront payment for the Centenario farm-in, and net cash outflow for the quarter was $58 million. The company held 16,223 dmt of saleable inventory.
The underground mine produced 388,568 tonnes of ore at a run rate of about 1.6 million tonnes per annum, with the company expecting a step to about 1.9 million tonnes per annum in the second quarter of FY27 and a target of 2.8 million tonnes per annum by the end of FY27. Ore processed was 508 kdmt at an average feed grade of 1.3% Li2O, and lithia recovery averaged 60%, compared with 63% in the June quarter. The company attributed this to contamination and variable quality in open pit stockpile feed. The average realised price was US$1,966/dmt SC6e, against US$1,880/dmt in the June quarter.
Kathleen Valley Expansion
The expansion lifts targeted steady-state production to a five-year average of about 780,000 dmt a year on an SC5.4 basis and reduces targeted average steady-state operating costs to $880/dmt at the range mid-point, both from FY30. The cost range is $840 to $920/dmt in real terms. First ore from Kathleen's Corner Underground is expected in the first quarter of FY28. Managing Director and CEO Tony Ottaviano said the company is looking through short-term lithium price movements and investing in the operation.
Centenario Lithium Brine Farm-In
Liontown entered a staged farm-in to the Centenario lithium brine project in Argentina, its initial entry into lithium brine. Mr Ottaviano said the arrangement complements the hard rock operation at Kathleen Valley and gives another avenue for growth.
Production Guidance
The company said annual production is expected to meet FY27 guidance as the underground ramp-up continues and supports increasing production through the remainder of the year.