Key Highlights
- Beacon Minerals (ASX:BCN) reported a 430,200-ounce gold Ore Reserve at the Iguana deposit.
- The estimate covers 11 million tonnes at an average gold grade of 1.20 grams per tonne.
- Beacon processed Iguana and Geko ore in a blend at its Jaurdi Facility during the September quarter.
- The development brings mine preparation, road haulage and processing capacity into the same operating plan.
Beacon Minerals (ASX:BCN) has begun commissioning additional tank capacity at its Jaurdi processing operation in Western Australia, where it has been blending ore from Iguana and Geko. An updated Ore Reserve reported in August 2026 increased estimated contained gold at Iguana to 430,200 ounces, expanding the deposit’s role in the company’s mine plan.
The Iguana reserve
Beacon reported an Ore Reserve of 11 million tonnes at 1.20 grams per tonne gold, representing a 325% increase in contained gold from the previous estimate. The update followed a drilling campaign that added information on the geometry and grade of the deposit.
Contained ounces quantify the gold estimated to be present in the ore. The amount eventually recovered also depends on Mining losses, ore dilution and metallurgical performance. As Beacon sequences development, those factors will affect the relationship between ore mined at Iguana and gold produced at Jaurdi.
Linking Lady Ida to the mill
Beacon hauls Iguana ore from Lady Ida to Jaurdi for treatment. The company processed it together with Geko ore during the September quarter. How much the mill draws from each source depends on the mine schedule, stockpiles and the grade of ore available.
An upgrade at an operating mill has to be coordinated with day-to-day production. The expanded processing circuit adds capacity for leaching and adsorption as the company manages the ore blend.
Operations and Capital requirements
In its September-quarter reporting, Beacon discussed Iguana alongside its existing production and exploration activities. As the mine plan advances, haulage, plant availability and recovery will influence the operating contribution from Iguana. Gold prices and site costs remain relevant to the returns on those tonnes.
The company also declared a fully Franked Dividend of five Australian cents per share in November. The dividend is a separate corporate decision alongside the operational work at Lady Ida and Jaurdi.
Commissioning and September output
Beacon reported that wet commissioning of the expanded leach and adsorption tank capacity began on 13 October 2026. The company reported milling rates equivalent to 1.2 million tonnes a year during the first weeks of commissioning. Throughput during commissioning is an early operating measure and will depend in subsequent periods on plant availability and the ore blend.
The September quarter provides a baseline for comparison. Beacon reported that Jaurdi milled 265,877 tonnes and produced 6,250 ounces of gold on a 100% basis. The reported share attributable to Beacon under the Lady Ida joint venture was 3,303 ounces. The two figures describe plant output and Beacon’s share, respectively.