Key highlights
- DXN (ASX:DXN) secured a modular cable landing station contract worth approximately AUD 4.8 million.
- The project represents the internet customer’s fourth order with DXN.
- The company expects the modules to reach the Pacific site in Q1 FY28.
DXN (ASX:DXN) rose 11.63% to AUD 0.24 during trading on 20 November 2026. Across the broader market, the S&P/ASX 200 was at 8,632.80 at 11:59 a.m. Sydney time. All 11 sectors were lower. The prefabricated modular data centre specialist announced a Pacific cable landing station contract on 11 November 2026.
Fourth cable landing station order from the same customer
DXN announced on 11 November 2026 that it had signed a binding contract with a global internet company for a modular cable landing station. The agreement is valued at approximately AUD 4.8 million, equivalent to about USD 3.4 million in the company’s presentation. The station is intended for a site in the Pacific region under US jurisdiction, and the work includes both Supply and commissioning.
This is the fourth order DXN has received from the same customer. The company has standardised the engineering solution for that customer’s deployments. DXN expects reuse of the design to save time and costs across engineering, manufacturing, supply chain and delivery activities. DXN identified the customer as a global internet company.
Integrated systems and factory testing
The turnkey scope includes design, engineering, module manufacture and commissioning. DXN will integrate the station’s power supply, cooling, fire suppression, security and monitoring systems into its prefabricated modules. The equipment is designed around the availability requirements of cable landing infrastructure. The modules are due to go through factory acceptance testing before they are sent to the Pacific site.
At the time of signing, DXN expected Manufacturing activity to start immediately and planned to use facilities in Malaysia and Western Australia. Its timetable places delivery to the site in the first quarter of FY28. The contract covers a complete solution, so the supply of the modules forms one part of a scope that also includes commissioning.
The initial work includes preparing individual systems for integration into the modules. The factory acceptance stage precedes dispatch of the assembled equipment, and DXN’s scope continues through commissioning after the modules reach the site. The company identified controlled factory testing and the use of prefabricated modules as features of its approach to supplying remote installations.
Sector context
The information technology sector was down 4.84% during the session. DXN’s project is part of the physical infrastructure used by subsea cable operators. Cable landing stations house equipment where undersea links connect to land-based networks. For this installation, the company is applying a modular approach in which the key systems are integrated and tested at the factory before shipment.
Risks investors are watching
The announced delivery schedule depends on completing manufacture, factory acceptance testing and shipment to the site. DXN identified remote or logistically challenging sites as settings where it uses the modular approach. The disclosed schedule gives a site-delivery quarter. The contract value applies to the overall project, including commissioning activities in addition to design and supply.
What to watch ahead
The next schedule markers are progress at the manufacturing facilities, completion of factory acceptance testing and shipment of the modules for site delivery. DXN has set Q1 FY28 as the delivery window. The final stage of the contract scope includes commissioning the integrated systems at the location designated by the customer.
The delivery timetable
The agreement adds a fourth deployment for an established customer, using a design DXN has standardised for that relationship. The work now moves through manufacturing and testing before the targeted FY28 site delivery.