  • NEXTDC Limited, a member of the S&P/ASX 50 since the September 2026 rebalance, has moved from a sharp guidance cut to an unsolicited stake purchase by two.
  • On 21 October 2026, after a trading halt, NEXTDC said Jemena Electricity Networks had suspended parts of its 66kV network augmentation works supplying the M3 campus in.
  • The work suspension delayed the next increase in electricity Supply to the M3 campus.
  • NEXTDC cut FY27 net Revenue guidance to A$475 million to A$500 million, from A$615 million to A$640 million, and underlying EBITDA guidance to A$245 million to A$265.

NEXTDC (ASX:NXT) develops and operates data centres in Australia and is expanding into Asia.

A turbulent few weeks for a data centre heavyweight

NEXTDC Limited, a member of the S&P/ASX 50 since the September 2026 rebalance, has moved from a sharp guidance cut to an unsolicited stake purchase by two industry giants in a fortnight.

The approach does not amount to a takeover. NEXTDC's board described the raid as opportunistic and said it had received no Takeover proposal, while the buyers reportedly told investors they had no intention of submitting a control proposal at this time.

What NEXTDC does

NEXTDC develops and operates data centres in Australia and is expanding into Asia. It sells colocation space, power and connectivity to cloud providers, enterprises and government customers, and targets artificial intelligence workloads.

Its Business model depends on contracting capacity in advance, building facilities, securing grid power and then converting contracted megawatts into billing revenue over several years.

From power delay to share raid

On 21 October 2026, after a trading halt, NEXTDC said Jemena Electricity Networks had suspended parts of its 66kV network augmentation works supplying the M3 campus in Melbourne. It does not expect works to resume before February 2027, and the next increase in grid supply to M3 is now expected in FY28.

NEXTDC cut FY27 net revenue guidance to A$475 million to A$500 million, from A$615 million to A$640 million, and underlying EBITDA guidance to A$245 million to A$265 million, from A$385 million to A$410 million. It paused new development projects and land acquisitions.

Ahead of its annual general meeting, the board announced renewal plans, including the eventual retirement of chairman Douglas Flynn, a voluntary ten per cent cut to directors' fees and the Withdrawal of resolutions on a higher fee pool and chief executive incentives.

The financial picture

FY26 results, released on 27 August 2026, showed total revenue of A$496.5 million, up 16 per cent, and underlying EBITDA of A$248.8 million, up 15 per cent. Statutory net profit was A$82.1 million, compared with a loss of A$60.5 million a year earlier.

Contracted utilisation reached 740.1MW and the forward order book stood at 565.1MW. Capital Expenditure hit a record A$3.4 billion, and pro forma Liquidity was put at A$8.7 billion after significant capital raising.

Revised FY27 capital expenditure guidance is A$4.5 billion to A$5 billion.

Risks and uncertainties

The clearest risk is power. The M3 timetable rests on an indicative estimate from Jemena, and the company has warned that service-level credits could push EBITDA lower still. Further grid, planning or community delays at other sites would compound the problem.

Funding needs remain heavy given the scale of capital expenditure, and the business carries execution risk across multiple large builds. The arrival of two strategic shareholders introduces uncertainty about future corporate activity, which could cut either way for existing investors.

Milestones to watch

The Annual General Meeting on 20 November 2026 is the next key date. The board has said it will announce the outcome of its capital expenditure review by then, and shareholders will vote on the remaining resolutions.

Beyond that, developments ahead include for any resumption of Jemena's works from February 2027, appointment of a new chair and additional director in early 2027, any further moves by Goodman or Digital Realty, progress on capital recycling, and the conversion of contracted capacity into billing during FY27 and FY28.