Highlights

  • NEXTDC lifted FY27 underlying EBITDA guidance to AUD 260–275 mn and kept planned Capital Expenditure at AUD 4.5–5 bn.
  • Macquarie Technology Group directed AUD 186.2 mn of FY26 growth capital expenditure towards construction of its IC3 SuperWest facility.
  • DXN designs prefabricated data centres that customers can expand by adding modules or increasing power and cooling as needed.
  • All three stocks rose on 23 November 2026, with DXN posting the largest percentage gain of the group.

NEXTDC Limited (ASX:NXT), Macquarie Technology Group Limited (ASX:MAQ) and DXN Limited (ASX:DXN) all gained on 23 November 2026. Their businesses show three ways to add data centre capacity. NEXTDC is prioritising space customers have already contracted. Macquarie Technology is building one Sydney Facility while holding land for a separate proposed campus. DXN manufactures modules for customers that want to install computing infrastructure at their own sites.

NEXTDC Raises Earnings Guidance and Keeps Spending Range Steady

NEXTDC shares rose 1.78% to AUD 9.17. On 20 November, the company lifted the lower end of its FY27 net Revenue forecast by AUD 10 mn, taking the range to AUD 485–500 mn. It also raised underlying EBITDA guidance to AUD 260–275 mn from AUD 245–265 mn, citing higher revenue expectations and cost savings.

The company kept its capital expenditure range at AUD 4.5–5 bn after reviewing which projects to prioritise. At its S4 Sydney site, customers have contracted 250 MW of the planned 365 MW of IT load, and construction is underway on a 115 MW first phase. The revised earnings guidance excludes the contribution from affected customer contracts at M3 Melbourne.

Macquarie Technology’s FY27 Outlook Hinges on SuperWest Timing

Macquarie Technology Group shares gained 1.45% to AUD 49. The group spent AUD 186.2 mn on IC3 SuperWest in FY26, accounting for most of its AUD 193.3 mn in growth capital expenditure. In August, the company said construction was on schedule and within budget. Its forecast for modest FY27 EBITDA growth assumes the first phase begins generating revenue in the second half.

The group also completed the purchase of a site in Macquarie Park in August for a separate proposed campus with capacity of around 200 MW. The site Acquisition gives Macquarie Technology room for a future development, while SuperWest is the project already under construction.

DXN Offers Customers a Way to Expand in Stages

DXN shares rose 9.30% to AUD 0.235. The company builds prefabricated data centres to customer specifications and also offers colocation at operating facilities. A customer that needs more space can install a second module alongside the first. Another option is to start with room for more racks and add power and cooling as those racks come into use.

DXN also designs modules with direct-to-chip liquid cooling for high-performance computing. The choice of cooling and the amount of capacity installed at the outset depend on the customer’s workload and expansion plans.