Key highlights

  • DXN (ASX:DXN) announced a binding contract worth approximately AUD 4.8 million for a modular cable landing station on 11 November 2026.
  • The order is the fourth from the same global internet customer and covers design, manufacturing, Supply and commissioning.
  • DXN expects to use its Malaysian and Western Australian facilities and is targeting site delivery in the first quarter of FY28.

DXN (ASX:DXN) gained 17.02% to AUD 0.275 during the 24 November 2026 Trading session as the benchmark S&P/ASX 200 rose 1.56% to 8,704.50. DXN manufactures and operates modular data centre infrastructure for customers across the Asia-Pacific region. On 11 November, it announced a binding contract to provide a cable landing station for deployment at a Pacific site under US jurisdiction.

A fourth order from the same internet customer

The contract disclosed on 11 November 2026 is valued at approximately AUD 4.8 million, or approximately USD 3.4 million. A global internet company commissioned the station, the fourth order placed with DXN by the same customer. The contract covers the design, engineering, manufacturing, supply and commissioning of the modular facility.

DXN has standardised elements of its engineering design for the customer across repeat orders. Those standards cover the project from design through manufacturing, supply chain and delivery. The configuration uses the company’s prefabricated module platform, which brings the station’s power and cooling equipment, fire suppression, security and monitoring systems together in one design.

The turnkey scope includes the prefabricated enclosures and their operating equipment. The units are assembled around that equipment before commissioning at the destination.

Factory work before delivery to a Pacific site

DXN expected Manufacturing to begin immediately after signing and plans to use facilities in Malaysia and Western Australia. Factory acceptance testing is scheduled before the modules are delivered to the Pacific site. That testing is a distinct milestone from the subsequent commissioning work included in DXN’s contract.

The site delivery target is the first quarter of FY28. The destination is a Pacific location under US jurisdiction. The modular assembly model means work on the facility’s core systems takes place before delivery, with the site phase following transport. The company identified the customer by Business type and kept its name private.

DXN will use its standardised engineering approach for the customer’s new deployment. DXN identified repeatable design, manufacturing and sourcing as areas where the standard can reduce work between projects. The manufacturing plan spans two countries.

The infrastructure behind subsea connectivity

A cable landing station is the onshore Facility where a subsea communications cable connects with terrestrial network equipment. Its operating requirements include stable power, cooling and monitoring for the equipment inside. The station order sits in DXN’s modular infrastructure business, which also supplies systems to telecommunications, mining, defence and other sectors.

DXN’s wider operations include a data centre in Darwin providing colocation, monitoring and managed hosting. Its service division also provides facility management and monitoring for data centres and satellite ground stations. The Pacific contract is a project to supply and commission infrastructure for a customer.

Cable stations serve a different function from colocation data centres, even though both need monitored power and environmental controls. The station supports the physical connection to a subsea network. Colocation customers use space within a facility to house their own equipment.

Risks investors are watching

Delivery depends on DXN coordinating manufacturing, factory testing and transport to the Pacific site. The integrated systems undergo testing before dispatch and commissioning at the destination. The first quarter of FY28 is DXN’s expected delivery period for the prefabricated modules at the site. The 11 November terms give the approximate contract value and delivery window, with billing and Revenue timing left unspecified.

What to watch ahead for the station

Manufacturing at the two facilities and factory acceptance testing are the next operational milestones. After testing, the modules are expected to move to the Pacific deployment site for installation and commissioning. The first quarter of FY28 is the timetable reference for delivery to the site.

DXN has included commissioning in the scope of work, with the published delivery target referring specifically to arrival on site.

From a repeat order to factory acceptance

The Pacific order extends a customer relationship through an additional station built on a standardised design. The immediate work is at the factories in Malaysia and Western Australia, with transport and on-site commissioning scheduled to follow. Delivery is the dated milestone DXN has identified for the project.