Key Highlights
- Iondrive (ASX:ION) engaged a processing partner to test about five tonnes of end-of-life permanent magnets.
- The campaign targeted roughly 1.4 tonnes of mixed rare earth oxides for Downstream qualification.
- Five government funding applications submitted by the October update totalled about USD 62.6 million.
- Quarter-end cash was AUD 5.1 million, and Iondrive had lodged an AUD 1 million research tax incentive claim.
Iondrive (ASX:ION), an Australian developer of technology for recovering critical minerals, outlined the next round of feedstock tests for a proposed US rare earth processing module in its September 2026 quarterly report. The 30 October release set out a programme to produce larger samples for downstream customers and described government funding applications and potential Debt and state incentives for the project.
Five-tonne magnet qualification campaign
Iondrive engaged Kingston Process Metallurgy to process about five tonnes of discarded permanent magnets using the company’s IONSolv process. The campaign aimed to produce about 1.4 tonnes of mixed rare earth oxides during the fourth quarter of calendar 2026. The material was intended for downstream customers to assess. Iondrive also expected the work to provide operating and engineering data before it committed Capital to a dedicated facility.
The company is targeting the recovery of neodymium, praseodymium and dysprosium. Earlier independent laboratory work on commercial US magnet feedstock recorded single-pass leach recoveries of 96.5% for neodymium, 96.5% to 97.3% for praseodymium and 93.5% to 93.6% for dysprosium. The company published those laboratory results alongside plans to establish overall recovery and operating conditions at a larger scale.
Design assumptions for an Oklahoma module
A technical and economic evaluation released in September updated the company’s November 2025 assessment. It modelled a US module handling approximately 2,400 tonnes of feedstock a year. The updated study used an assumed rare earth oxide feedstock grade of 30.66% and an overall process recovery of approximately 89%. Changes in the assumed feedstock composition, including its dysprosium content, informed the updated study alongside revised pricing and costs.
Iondrive’s proposed Supply chain would source magnet-bearing waste in the US, process it domestically and provide recovered materials to downstream customers. The Quarterly Report identified feedstock qualification, product acceptance, engineering and funding as steps required before deployment. Customer arrangements remained subject to product specifications, pricing and final commercial terms. Engineering work included plans to refine estimates of capital and operating costs.
Cash and potential financing
At the time of the October release, the company had filed five government funding applications. The USD 62.6 million aggregate was the amount sought. It was also exploring senior debt through the US Department of Agriculture’s Business and Industry programme and potential Oklahoma incentives of up to about USD 5.2 million. The state incentives were described as non-binding and linked to eligibility and performance requirements.
The company recorded net cash outflows of AUD 1.9 million during the quarter. Operating and investing outflows totalled AUD 2.2 million before other cash movements. The AUD 1 million Research and Development claim related to FY26 and had been lodged. The report presented that claim separately from quarter-end cash. The exercise of Options generated AUD 0.3 million of financing inflows during the quarter, followed by AUD 0.2 million in October. Iondrive attributed AUD 1.1 million of its operating and investing outflows to research and development on IONSolv, including the US magnet project.
Steps before a project decision
The work programme listed front-end engineering and continued funding discussions alongside the processing campaign. Iondrive planned to use the test material for downstream qualification and the results to assess feedstock and recovery assumptions. Grant and debt pathways remained subject to approvals and agreed terms. The report described those steps as part of the work towards an Investment decision on the proposed module.