Key Highlights

  • Infinity Metals (ASX:INF) suspended drilling at its wholly owned Yambacoona Tin Project after rainfall affected access.
  • Drilling began on 21 October 2026 and widespread rain started the following day.
  • More than 30 millimetres was recorded at nearby Brewarrina on the afternoon of 22 October.
  • The program was designed for up to 35 aircore holes, and the 26 October notice gave no restart date.

Infinity Metals (ASX:INF) holds mineral interests in Australia, the United States and Europe. On 26 October 2026, it reported suspending drilling at its Yambacoona Tin Project in New South Wales. The decision followed widespread rain in northern New South Wales and southern Queensland soon after the company began its first campaign on the target.

Rain interrupts access after drilling begins

Infinity began drilling on 21 October. Rain moved through the region the following day, with more than 30 millimetres recorded on the afternoon of 22 October at Brewarrina, about 25 kilometres northeast of the project. The company said it worked with local Stakeholders and suspended drilling while roads and tracks dried. It cited the need to prevent damage to infrastructure. Once the rig could be moved, the company planned to send it to another Job before returning to Yambacoona when appropriate. The notice gave no date for the rig’s return.

NSW approval and the first aircore campaign

On 6 October, Infinity announced that NSW Resources had approved its application for the proposed drilling. The company said it had secured access with landholders across the areas covered by the program and engaged a drilling contractor. In its 21 October commencement notice, it described a plan for up to 35 aircore holes. The campaign is reconnaissance work intended to test for alteration or mineralisation associated with a possible skarn system. Infinity’s approvals announcement estimated the bedrock at about 15 to 20 metres below the transported material covering the target.

The 6 October filing described the access agreements and the regulatory approval as the final preparations for drilling. The 21 October notice then confirmed the contractor started work on the wholly owned project.

How Infinity selected the target

Yambacoona lies about 60 kilometres east of Bourke. Infinity said geophysical work detected overlapping gravity and magnetic anomalies that informed the choice of target areas. The September activities report described plans for lines of shallow drill holes crossing those anomalies. The company identified four areas in its drilling submission and outlined expected hole depths of 15 to 75 metres. Two historical drill holes documented from the 1990s were in the northern part of the tenement and targeted a different part of the project. The October program focuses on geophysical targets the company says had never been drilled.

September funding and other project activity

Infinity reported cash of AUD 3.1 million at 30 September. During the quarter it issued 115 million shares in the second Tranche of its Placement and raised AUD 1.15 million, following Shareholder approval. The Quarterly Report also recorded an option to acquire a 100% interest in the Tule Canyon molybdenum and copper project in Nevada and additional claims at Swansea in Arizona. At Yambacoona, the NSW drilling approval and commencement both occurred after the September reporting period.

The 26 October filing records a pause after the campaign started. The company put the immediate emphasis on allowing the access tracks to dry and relocating the rig when it could move. The work remaining at the site is the proposed reconnaissance test of the concealed target.