Key highlights

  • VRX Silica completed the purchase of Arramall farm, where it plans to locate the Arrowsmith North processing plant and related infrastructure.
  • Western Australia granted a 21-year Mining Lease over part of the proposed land swap area at the Muchea silica sand project.
  • The Arrowsmith North feasibility study estimates about AUD 74.5 million in Capital Expenditure for a plant designed to process two million tonnes annually.

VRX Silica (ASX:VRX) shares rose 10.35% to AUD 0.032 during the Trading session on 23 November 2026. The benchmark S&P/ASX 200 stood at 8,597.80 points at 11:40 am AEDT. VRX Silica is a developer of Western Australian silica sand projects. Its 29 October 2026 quarterly update covered the planned Arrowsmith North plant relocation, the associated approvals and a new mining lease at Muchea.

Arramall becomes the proposed plant site

The September quarter update recorded the completion of the Arramall farm purchase. The property comprises approximately 2,091 hectares across two freehold lots, with the Arrowsmith North mining lease to the east and Brand Highway to the west. VRX plans to place the processing plant on previously cleared land on the farm. The site can also accommodate supporting infrastructure and has direct access to the highway for transport to Geraldton Port.

Changes to the Arrowsmith North approvals

Relocating the plant requires amendments to existing approvals. VRX completed targeted environmental and technical surveys to support the relocation and its environmental offset strategy. The process ran beyond the September quarter after state and federal regulators sought more information about the proposed change. Separately, the state granted the company’s tenement-holding Subsidiary a 21-year general purpose lease over part of the farm. Its prescribed uses cover the plant, access roads, stockpiles and other infrastructure, subject to standard conditions.

Muchea adds mining tenure

In October the state granted a new 21-year mining lease over part of the Muchea land swap area. The revised project area comprises the new lease and the retained portion of the original lease, following a partial surrender of existing tenure. VRX reported a total Muchea mineral resource of 208 million tonnes at 99.6% silica. It is targeting potential feedstock for ultra-clear glass applications at the project, about 50 kilometres north of Perth.

The land swap also changed the boundary of an area identified for possible conservation or offsets.

Silica sand markets

Arrowsmith North has a proved and probable ore reserve of 221 million tonnes at 99.5% silica. The project is designed to serve foundry, container glass and flat-glass customers, with an initial market focus on Asia. For resin-coated foundry sand, the company highlighted the deposit’s individual grains and their thermal stability. Muchea’s potential role in ultra-clear glass gives that project a different end market within the same commodity.

Foundry and glass customers specify different properties for the sand they buy. Foundries use sand in moulds and cores and assess properties such as how well grains withstand heat and pressure. Glassmakers pay close attention to purity and particle size because both affect the finished product.

Approvals and financing still in focus

VRX was seeking project funding through a potential combination of debt, Equity and prepaid offtake. The October update said the required capital was still to be secured. Quarter financing proceeds supported the farm purchase, early works and engineering, as well as work at Muchea and working capital. That corporate funding sits alongside the separate feasibility estimate for the Arrowsmith North plant and related project capital.

The October report identified placements of AUD 3.5 million to Nebari and AUD 1 million of additional Investment from the Delphi group. Proceeds contributed to work before construction.

What comes before trial shipments

VRX expected the outstanding amendment process to be completed during the December quarter at the time it published the update. It was targeting first production with early trial shipments in early 2028. The intervening steps include completing detailed engineering, securing project capital and advancing work on the plant site. The company recorded no substantive mining production or development activity in the September quarter.

Two projects at different stages

Arramall gives Arrowsmith North a proposed processing plant location and a route to port, while the lease grant at Muchea changes the ground available for future development. The next dated milestones concern Arrowsmith North, where the plant relocation and trial shipment schedule depend on progress through approvals, funding and construction.