- Unico Silver shares rose 1.56% to AUD 0.65 during the morning session on 22 July 2026 following its June-quarter update.
- The company reported assays from 121 drill holes covering 16,194 metres, with all results located outside the March 2026 Mineral Resource.
- Standout results included 11.25 metres at 1,301 grams per tonne silver equivalent at Breccia Puntudo and 52.3 metres at 378 grams per tonne silver equivalent at La Morocha SE.
- Exploration drilling has been completed for the current program, with work now focused on the maiden Pre-Feasibility Study scheduled for late Q3 2026.
- Unico Silver ended the quarter with AUD 55.07 million in cash and estimated funding for 6.15 quarters.
Unico Silver Limited (ASX:USL) shares increased 1.56% to AUD 0.65 during the morning session on 22 July 2026 after the company released its report for the three months ended 30 June 2026. The stock remained 47.73% higher over the previous year. The market response followed a favourable update covering high-grade gold-silver drilling at the Joaquin Project, progress toward a maiden Pre-Feasibility Study, a strategic land acquisition and a sizeable quarter-end cash position.
About Unico Silver
Unico Silver is an ASX-listed precious metals exploration company with a portfolio of gold and silver properties in Santa Cruz province, Argentina. Its principal assets include the Joaquin and Cerro Leon projects, which are located near AngloGold Ashanti’s Cerro Vanguardia mine and are connected by public Route 12.
The company’s combined Joaquin and Cerro Leon Mineral Resource currently stands at approximately 330 million ounces of silver equivalent. Joaquin hosts a March 2026 Mineral Resource of 167 million ounces of silver equivalent, while Cerro Leon contains a September 2025 Mineral Resource of 162 million ounces of silver equivalent.
Unico Silver’s current work is centred on advancing Joaquin toward a maiden Pre-Feasibility Study while continuing to assess extensions beyond the existing resource boundaries.
Drilling Extends Mineralisation Beyond the Current Resource
The June quarter marked the completion of the current exploration drilling campaign at Joaquin.
During the three-month period, Unico Silver reported assay results from 121 drill holes covering a total of 16,194 metres. These results were released across two announcements in May and June 2026 and included drilling at Breccia Puntudo, La Morocha SE and La Negra SE.
Importantly, all of the reported intersections sit outside the March 2026 Joaquin Mineral Resource.
Since drilling commenced in September 2025, the company has now reported results from 268 holes for a combined 38,661 metres.
The latest results extended gold-silver mineralisation across several prospects and confirmed that the mineralised systems remain open at depth and along strike. This provides scope for future resource growth when exploration drilling resumes.
Breccia Puntudo Delivers Its Best Hole to Date
At Breccia Puntudo, drilling focused on both infill and extension work along a structure extending approximately 3.5 kilometres.
The company reported its best hole to date at the prospect from JDD228-26, which intersected 11.25 metres at 1,301 grams per tonne silver equivalent from 127.4 metres.
Within this interval, a higher-grade section returned 6.8 metres at 1,934 grams per tonne silver equivalent from 131.2 metres. The broader intersection contained 15 grams per tonne gold and 8 grams per tonne silver, while the internal interval included 22 grams per tonne gold and 8 grams per tonne silver.
Other reported results at Breccia Puntudo included 12.7 metres at 1,178 grams per tonne silver equivalent from 56.9 metres in JDD235-26 and 15.7 metres at 363 grams per tonne silver equivalent from 84 metres in JDD256-26.
The company said the drilling confirmed high-grade gold mineralisation close to surface. Infill work was also intended to support the potential conversion of Inferred resources into the Indicated category for the Pre-Feasibility Study.
La Morocha SE Returns a Wide High-Grade Intersection
La Morocha SE also produced its best reported drill result to date during the quarter.
Hole JDD276-26 intersected 52.3 metres at 378 grams per tonne silver equivalent from 184.8 metres. This included 8.5 metres at 1,813 grams per tonne silver equivalent from 223.8 metres.
The broader intersection contained 3.3 grams per tonne gold and 100 grams per tonne silver. The higher-grade internal interval returned 18.3 grams per tonne gold and 256 grams per tonne silver.
The hole was located approximately 50 metres down-plunge from the original discovery hole, JDD028-25. According to the company, the result confirmed that gold grades increase at depth within this part of the system.
Mineralisation at La Morocha SE remains open both down-dip and along strike, and the company intends to return to the area when exploration drilling resumes in Q3 2026.
La Negra SE Broadens the Oxide Mineralised Footprint
Step-out drilling at La Negra SE intersected wide zones of oxide gold-silver mineralisation beyond the March 2026 resource boundary.
The reported holes were located as much as 250 metres southeast of the existing Mineral Resource.
Results included 73 metres at 90 grams per tonne silver equivalent from 21 metres in JDD171-26 and 78 metres at 137 grams per tonne silver equivalent from 91 metres in JDD240-26.
A further hole, JDD267-26, returned 74.2 metres at 94 grams per tonne silver equivalent from a depth of 1.8 metres.
These broad intersections extend the mineralised footprint at La Negra SE and sit outside the current Joaquin resource estimate. The mineralisation remains open at depth and along strike.
Attention Shifts From Exploration to the PFS
With the current exploration drill campaign complete, Unico Silver has moved its near-term focus toward the maiden Joaquin Pre-Feasibility Study.
The study is scheduled for completion in late Q3 2026.
Several workstreams are already underway. These include geotechnical drilling and interpretation to establish open-pit slope and design parameters.
The company is also advancing comminution and metallurgical testing to confirm processing assumptions and recovery pathways.
Phase 2 baseline environmental studies are progressing to support the Environmental Impact Assessment required for future mining approvals. Water-exploration drilling is also being undertaken as part of the project’s hydrological assessment.
Exploration drilling is expected to restart during Q3 2026, with future activity targeting extensions at La Negra SE and La Morocha SE.
The company plans to assess results reported outside the March 2026 resource for possible inclusion in a future Mineral Resource update.
La Mata Acquisition Secures Strategic Development Land
After the quarter ended, Unico Silver entered into a binding agreement to acquire a 100% interest in the La Mata estancia.
The property covers approximately 10,172 hectares of freehold land and hosts the La Morocha and La Negra Mineral Resources, together with prospective extensions.
The land also covers the company’s preferred locations for major infrastructure, including the processing plant, Tailings Storage Facility and haul roads.
The acquisition replaces a historical surface-rights arrangement established in 2017. That earlier agreement provided mining easement and usufruct rights over approximately 1,250 hectares and was due to expire in June 2034.
Permanent ownership of approximately 10,172 hectares gives Unico Silver a substantially larger area and greater flexibility for a possible standalone development.
The total consideration is US$12 million.
Unico Silver is required to pay US$3.5 million in cash within ten business days of execution, funded from existing cash reserves. A further US$2.5 million will be settled through the issue of fully paid ordinary shares.
Three deferred cash instalments of US$2 million each are payable 12, 24 and 36 months after execution.
The company described the transaction as an important de-risking step for the Joaquin Pre-Feasibility Study because it secures the land needed for both mineral resources and proposed development infrastructure.
Combined Resource Remains at About 330Moz AgEq
There was no change to Unico Silver’s Mineral Resource estimates during the June quarter.
The Joaquin Project contains a total Mineral Resource of 45.3 million tonnes at 115 grams per tonne silver equivalent, representing 167 million ounces of silver equivalent.
This includes an Indicated Resource of 34.5 million tonnes at 118 grams per tonne silver equivalent for 131 million ounces and an Inferred Resource of 10.8 million tonnes at 106 grams per tonne silver equivalent for 37 million ounces.
The Cerro Leon Project contains 31 million tonnes at 161 grams per tonne silver equivalent for 162 million ounces.
Together, Joaquin and Cerro Leon hold approximately 330 million ounces of silver equivalent.
The drill results reported during the June quarter are not included in these estimates.
Cash Position Supports Ongoing Study Work
Unico Silver ended the quarter with AUD 55.068 million in cash and cash equivalents, compared with AUD 62.759 million at the beginning of the period.
The company reported a net operating cash outflow of AUD 349,000.
Exploration and evaluation expenditure was AUD 8.604 million, primarily linked to infill and extension drilling at Joaquin and work supporting the feasibility study.
Net investing cash outflow amounted to AUD 8.419 million after AUD 185,000 in proceeds from the sale of bonds.
Financing activities generated AUD 1.081 million during the quarter. This included AUD 1.094 million from the exercise of options, partly offset by AUD 13,000 in related transaction costs.
During the period, 4,141,176 options and 400,000 performance rights were exercised, raising AUD 1.09 million before costs.
Staff costs totalled AUD 113,000, while administrative and corporate expenditure was AUD 672,000 in the quarterly activities report. The Appendix 5B recorded administration and corporate payments of AUD 725,000.
Payments to related parties totalled AUD 303,000, comprising AUD 241,000 in directors’ fees and AUD 62,000 paid to Vistra Australia for corporate accounting and company secretarial services.
Based on quarterly operating and exploration outgoings of AUD 8.953 million, the company estimated that it had sufficient funding for approximately 6.15 quarters.
Unico Silver reported no loan facilities or other financing arrangements at quarter-end.
OTCQX Upgrade Expands U.S. Market Visibility
During the June quarter, Unico Silver upgraded its United States quotation from the OTCQB Venture Market to the OTCQX Best Market under the ticker USLRF.
The OTCQX quotation is intended to provide increased visibility among North American investors and broader access to the United States capital market.
The company’s primary ASX listing remains unchanged.
The upgrade did not involve the issue of new shares and had no impact on existing shareholders.
What This Means for Investors
Unico Silver’s quarterly update was favourable in terms of exploration progress and project development.
Drilling extended mineralisation beyond the March 2026 resource at Breccia Puntudo, La Morocha SE and La Negra SE, while two prospects returned their best holes to date.
The transition toward Pre-Feasibility Study workstreams marks a change in emphasis from resource expansion to development assessment.
The La Mata acquisition adds strategic importance by securing permanent ownership of land covering mineral resources and preferred infrastructure locations.
The company’s AUD 55.07 million cash balance provides funding for current technical studies, staged acquisition payments and future exploration.
However, the project remains at the study stage. The maiden Pre-Feasibility Study has not yet been delivered, and results outside the present resource require further evaluation before they can contribute to a future update.