Highlights
• Tungsten Mining released the Watershed feasibility study and accompanying project video.
• The study reports a Probable Ore Reserve of 36.6 million tonnes.
• Total pre-production Capital is estimated at approximately AUD 264.4 million.
• The company has not made a final Investment decision or secured binding offtake.
Tungsten Mining NL (ASX:TGN), an Australian tungsten project developer, released a Definitive Feasibility Study and accompanying video for its Watershed project in Far North Queensland on 16 November 2026. The study reported a Probable Ore Reserve of 36.6 million tonnes grading 0.124% tungsten trioxide and total pre-production capital of about AUD 264.4 million. The company has not made a final investment decision, and funding and binding offtake arrangements remain outstanding.
Reserve and Production Basis
The feasibility study reports a 13.1-year processing period and forecast life-of-mine production of 31,279 tonnes of tungsten trioxide. Approximately 90% of the mill-feed production target comes from Probable Ore Reserves, with the remaining approximately 10% supported by Inferred Mineral Resources. That latter component has a lower level of geological confidence, and conversion into a higher-confidence category is not guaranteed. The study was prepared to a feasibility-study standard under the 2012 JORC Code. Its production and financial estimates are projections dependent on technical, cost, price and scheduling assumptions rather than outcomes already achieved.
Economics Depend on Stated Price Assumptions
At an assumed life-of-mine average ammonium paratungstate price of USD 1,500 per metric tonne unit, the company reported a pre-tax net present value at an 8% discount rate of approximately AUD 1.569 billion and an internal rate of return of 70%. These are modelled project measures, not Revenue or Earnings recorded by the company. Their sensitivity to tungsten prices, currency exchange, operating expenditure, construction costs and recoveries is material. The study also reports forecast pre-tax payback of 18 months from first revenue. Such forecasts remain conditional on the mine being financed, built and operated as assumed.
Capital Requirements Before Construction
The total pre-production capital estimate comprises roughly AUD 57.8 million previously committed to work and AUD 206.6 million of go-forward capital. The company has received non-binding indicative Debt terms supporting up to 70% project gearing, but non-binding proposals do not constitute committed financing. The associated corporate announcement warns that additional funding cannot be guaranteed on acceptable terms. Financing structures may also involve Equity or strategic participation. The distinction between Capital Expenditure requirements and available cash or finance commitments is important; a completed technical study does not, by itself, fund construction.
Final Decision and Development Timetable
Tungsten Mining has reported principal project approvals and early site work as it seeks to progress towards a final investment decision. Binding financing and offtake agreements are among the key remaining commercial steps. The company has indicated a target of first production in June 2027, subject to its development conditions and execution schedule. The project video is intended to illustrate the development plan and does not supersede the detailed feasibility study. Readers should rely on the formal technical disclosure for reserve, production, funding and cautionary information rather than treating visual material as independent evidence of project economics.
Key Insights
The Watershed study provides a quantified reserve, estimated capital needs and projected economics. Those figures remain conditional forecasts: financing, binding offtake and a final investment decision are necessary steps before the proposed mine can proceed.