Key highlights
- Podium Minerals (ASX:POD) shares fell 9.09% to $0.02 during the Trading session on 26 November 2026, while the S&P/ASX 200 gained 0.76%.
- Phase 3 validation showed an average overall 3E recovery of 80% across six composites.
- Concentrator product grades ranged from 64 to 114 g/t 3E.
Podium Minerals (ASX:POD) shares fell 9.09% to $0.02 during the trading session on 26 November 2026, while the S&P/ASX 200 index was up 0.76% at 8,758.60. Podium Minerals is a platinum group metals developer with the Parks Reef PGM Project in Western Australia. Its most recent update, on Phase 3 metallurgical validation, was dated 19 November 2026.
Validation Results
Podium said its Phase 3 validation reproduced the optimised Concentrator performance reported in August 2026 across six sulphide composites spanning about 1km of the proposed Target Starter Mine #1 area. Overall 3E recoveries ranged from 74% to 84%, averaging 80%, with copper recoveries of 72% to 85%.
All composites within the expected baseload feed-grade range achieved at least 80% 3E recovery, and operating conditions were unchanged across tests.
Product Grades and Flotation
Concentrator product grades ranged from 64 to 114 g/t 3E, compared with 97 g/t in August, and upgrade ratios averaged 51 times. A total of 163 individual flotation stage results conformed closely to a single performance relationship (R² = 0.957).
Composites had head grades of 1.32 to 2.07 g/t 3E and widths of 6.2 to 13 metres, with PRDD013 blended below the baseload range to test lower grades.
Flowsheet and Next Steps
The Concentrator combines a flotation circuit with a PGM Value Recovery Circuit that treats magnetite in the tailings using a conventional cyanide leach. The August optimisation delivered a 31% relative improvement in flotation performance.
Phase 3 continues with deep drill core samples, mineralogical characterisation, comminution testing and engineering data. The company referred to a proposed Australia–US PGM Supply chain with PGM Processing LLC, under a non-binding MOU dated 14 September 2026.
Sector Context
PGM developers use metallurgical testwork to establish recoveries and product quality before feasibility studies, and results from small composites do not always scale to commercial operations.
Risks Investors Are Watching
Testwork is laboratory scale, the Downstream arrangement is a non-binding MOU and no development decision has been made. Funding and approvals are still required.
What to Watch Ahead
Attention is on the remaining Phase 3 workstreams, development studies at Parks Reef and the status of the proposed US supply chain.
Closing Perspective
Podium's validation reproduced its August recovery results across a wider set of samples. It was dated 19 November 2026, so the 26 November share move is not tied to it.