Highlights
• FY27 production guidance of 125–140 koz Au at an AISC of A$3,400–$3,600/oz confirmed.
• Construction of a new 3.0 Mtpa processing plant at Davyhurst is underway, with commissioning expected in the March 2028 quarter.
• Ora Banda holds A$507 million in available liquidity, comprising A$207M cash and a A$300M undrawn revolving Credit facility.
• 1.84 Moz Mineral Resource and 610 koz Ore Reserve underpin a growth pathway to 300 koz per annum by FY29.
Ora Banda Mining (ASX:OBM) used its 2026 Annual General Meeting to update shareholders on the progress of its DRIVE to 300 aspirational gold production target, confirming FY27 guidance of 125–140 koz at an AISC of A$3,400–$3,600/oz. The company delivered a record 141 koz in FY26 — its highest full-year output — while growing Mineral Resources by 75% and Ore Reserves by 159% year-to-date through its A$75 million annual exploration programme.
New Mill and Infrastructure Underway
The centrepiece of OBM's growth strategy is the construction of a new standalone 3.0 Mtpa processing plant at Davyhurst, located adjacent to its existing 1.2 Mtpa mill. Capital Expenditure of A$240M is allocated to the new mill in FY27 alone, with a combined nameplate capacity of 4.2 Mtpa expected to be operational during FY29. Infrastructure upgrades including sealed airstrips, expanded accommodation to over 900 rooms, and a new on-site assay laboratory are also underway, targeting material reductions in operating costs.
Multiple Ore Sources and Exploration Momentum
Ore flow from the Waihi Underground (commenced September 2026 targeting the high-grade Golden Pole zone), Round Dam Open Pit (PFS complete, FID expected 2H FY27), and ongoing operations at Riverina and Sand King will support the transition through the mill-constrained period ahead of the new plant commissioning. The Little Gem prospect — located along a 7.5 km trend from Riverina to Sunraysia — has expanded to 2.6 km strike and a maiden Mineral Resource is targeted in the December or March 2027 quarter.
Balance Sheet and Capital Management
Ora Banda carries no Debt and held A$207M cash at 30 September 2026, with the recent upsizing of its revolving credit Facility to A$300M lifting total Liquidity to A$507M. Downside price protection is in place through put options at A$6,000/oz over 99,996 oz from November 2026 to October 2027, and partial collars for November 2027 to June 2028.
Key Insights
Ora Banda confirmed guidance of 125,000–140,000 ounces for FY27. The company expects commissioning of its new Davyhurst mill in the March 2028 quarter.