Highlights
- The company has previously reported Probable Ore Reserves, but has not made a final Investment decision and has no production.
- The company says it adopted a reset in the June quarter to cut spending and pursue a lower-capital development path.
- About AUD 2.71 million of convertible notes held by C/M Capital had their maturities extended by 12 months into 2028.
- Beyond that, investors will be watching for partnering news, Royalty financing outcomes and progress on the Mining Lease proposal.
Magnetite Mines Limited (ASX:MGT) is trying to keep its Razorback iron ore project in South Australia moving on a much smaller budget. After a Leadership change and what it called a strategic reset in mid-2026, the company released a new scoping study configuration in September and raised about AUD 1.32 million in October, but its September quarter report showed less than one quarter of funding on hand before that raise.
What Magnetite Mines does
Adelaide-based Magnetite Mines is developing Razorback, a large magnetite deposit in South Australia, with the aim of producing high-grade concentrate suited to direct reduced iron (DRI) steelmaking, a lower-emissions route to steel. According to its FY2026 Annual Report dated 30 September 2026, Razorback and the neighbouring Iron Peak deposit hold a combined mineral resource of about 3.84 billion tonnes at 17.40% iron, of which about 1.97 billion tonnes is Indicated and about 1.86 billion tonnes Inferred.
The project was granted Major Project Status by the Australian Government in February 2026.
Strategic reset and new scoping study
Tim Dobson stepped down as managing director on 26 May 2026 and Scott Lowe became executive chair on 1 July.
The September quarter report notes the company is not currently reporting an updated production target or forecast financial information. Next steps include drilling to convert Inferred material to Indicated, metallurgical testwork with saline water, and rail and port engineering ahead of a pre-feasibility study, all subject to funding. A mining lease proposal is under discussion with the state's Department of Energy and Mining.
By 30 September 2026, cash had fallen to about AUD 801,000 after operating outflows of about AUD 1.03 million, which the company said included one-off termination payments. It estimated 0.68 quarters of funding at that date.
On 28 October the company announced a fully subscribed share purchase plan raising about AUD 824,500 and a top-up Placement of about AUD 492,000, both at AUD 0.012 a share, with one free attaching option exercisable at AUD 0.015 for each new share, subject to Shareholder approval. Funds are earmarked for Razorback, partnering initiatives, possible acquisitions, exploration and working capital. The company is also evaluating royalty financing with ProspEx Group.
Share Trading on 16 November
That last price is below the AUD 0.012 issue price of the October raising.
Risks and milestones
Razorback is a large, capital-intensive project, and progressing to pre-feasibility and beyond will require substantially more funding or a strategic partner. Further Equity raisings, option exercises or note conversions would dilute existing holders. Magnetite markets, DRI Demand and infrastructure costs are additional uncertainties.
The Annual General Meeting on 30 November 2026 is scheduled to consider the attaching options, the note-extension Options and other resolutions.