Key Highlights
- True North Copper’s pre-feasibility study outlines a four-year open-pit Mining plan focused on sulphide material at Cloncurry.
- The study establishes a Probable Ore Reserve of approximately 3.5 million tonnes grading 0.86% copper and 0.24 grams per tonne gold.
- The study estimates AUD 8 million in pre-production Capital and AUD 45 million in working capital.
- True North targets a final Investment decision between the December 2027 and March 2028 quarters, subject to approvals and funding.
True North Copper (ASX:TNC) has completed a pre-feasibility study for the Cloncurry Copper Project in northwest Queensland. The study examines four years of open-pit mining using existing regional processing infrastructure and sets out the initial capital and Working Capital requirements. The company is advancing approvals and evaluating toll-processing arrangements before a possible investment decision.
Mine design and production targets
The study outlines a sulphide-focused plan with a life-of-mine production target based on approximately 49,000 tonnes of contained copper equivalent in 5.3 million tonnes of scheduled material. It targets annual output of 11,000 to 13,000 tonnes of copper equivalent in the first three years. The initial mine plan draws on approximately five million tonnes of the roughly 20 million tonnes in the project’s mineral resource inventory.
On a contained copper-equivalent basis, the target draws approximately 79% from Probable Ore Reserves, 11% from Indicated Mineral Resources outside the reserve and 10% from Inferred Mineral Resources. True North discloses lower geological confidence in the Inferred material. The company estimated seven months from a final investment decision to commercial production in the study schedule, subject to approvals and funding. The study gives pre-feasibility cost estimates an accuracy range of approximately plus or minus 25%.
The Cloncurry Probable Ore Reserve
The reserve totals 3.52 million tonnes at 0.86% copper and 0.24 grams per tonne gold, equivalent to a grade of 1.10% copper on the study’s combined-metal basis. It contains an estimated 30,400 tonnes of copper and 27,000 ounces of gold. The study expresses the combined contained metal as approximately 39,000 tonnes of copper equivalent.
The reserve assumes conventional open-pit mining and regional toll processing. The estimate incorporates mining dilution of approximately 5% and mining recovery of 86%. The study includes material from Mongoose-Taipan, part of which is subject to the Carpentaria joint venture. True North holds about 36% of that venture, and the study’s financial evaluation includes the full Mongoose-Taipan contribution without adjusting for the ownership split.
Processing, capital and approvals
True North estimated AUD 8 million in pre-production capital and AUD 45 million in working capital. The study assumes existing regional toll-processing infrastructure, with the company continuing to assess commercial arrangements. Its flotation assumptions include average recoveries of 81.9% copper and 72.4% gold across sulphide and transitional material. The study also assesses a separate leaching route for oxide material. Its mine plan spans open pits at Wallace North, Mongoose-Taipan, Great Australia and Orphan Shear, with a total movement estimate of 28.4 million tonnes.
Work planned for the first half of 2027 includes metallurgical tests at Wynberg and refinement of mine planning, processing and cost assumptions. The company intends to advance environmental studies and approvals, including the grant of the Mongoose mining lease. It also plans resource extension drilling at Wallace North and Mongoose-Taipan.
The timetable for a decision
True North is targeting a final investment decision between the final quarter of 2027 and the first quarter of 2028. The timing depends on approvals and funding, with processing arrangements still under evaluation. Permitting and technical work will continue alongside commercial discussions.