- Kore Potash (ASX:KP2) shares were 8.45% lower at $0.065 during the 27 November 2026 session.
- The company is working with the Republic of Congo on applying the Mining Convention under the new Mining Law.
- Two parties are engaged in the Formal Sale Process, and cash was about US$6.4 million at 30 September 2026.
Kore Potash plc (ASX:KP2) shares were trading 8.45% lower at $0.065 during the Trading session on 27 November 2026, while the S&P/ASX 200 index was at 8,786.20, up 0.26% or 22.40 points. Separately, the company released its review of operations for the September 2026 quarter on 30 October 2026. Kore Potash owns 97.58% of the Kola Potash Project and the Dougou Extension Potash Project in the Sintoukola Basin in the Republic of Congo.
Mining Convention and New Mining Law
Efforts in the quarter were largely focused on obtaining clarity and agreement on the practical application of the Mining Convention between the Republic of Congo and the company’s subsidiaries in light of the new Mining Law, Law No. 1-2026 of 18 April 2026. The company said there were numerous constructive meetings with the Ministry of Mining Industries and Geology, including a multi-ministerial working group, and that discussions on formalising the way forward are continuing.
Through a working group established by the Minister, the company, the financing team and the Government jointly evaluated the impact of the new Mining Law on the Kola financial model and its bankability. Chief Executive André Baya said clarifying the position is essential to enable the Formal Sale Process to proceed.
The company said the Kola Project is of importance, scale and strategic location, at a time when the security of the world’s food Supply remains at the mercy of international disruptions. It said the remainder of 2026 promises to be significant as it clarifies the new mining law while progressing Kola and the Formal Sale Process.
Formal Sale Process and Financing
The company commenced the Formal Sale Process on 4 November 2025 after approaches from two parties. One party suspended its interest on 27 February 2026 for internal reasons, the other remains engaged in due diligence, and a new party approached on 8 June 2026 and has begun due diligence, so two parties are currently engaged.
The company continues to engage with OWI-RAMS GmbH on non-binding term sheets signed on 10 June 2025 for the total funding requirement of the Kola Project. OWI-RAMS indicated it is encouraged by progress, and discussions with a prospective strategic partner that would both invest and operate the mine continue to advance.
The term sheets signed with OWI-RAMS cover the total funding requirement of the Kola Project, with a central element being the strengthening of Kore Potash’s managerial capacity to deliver the project. The introduction of an experienced operating partner is a key consideration under the term sheets, and the company said OWI-RAMS was kept informed of developments in the Republic of Congo.
Engineering, Environmental Work and Cash
Front-End Engineering Design continues for the underground design because of a change in the supplier of the vertical hoisting system, while the Environmental and Social Impact Assessment has been temporarily paused and is expected to resume once the strategic investors confirm their required design changes. The company released its half-year report for the six months ended 30 June 2026 on 11 September 2026.
Cash held at 30 September 2026 was about US$6.4 million. Kore Potash is listed on the AIM, the ASX, the JSE and A2X.
Early works had been completed previously, and the change in the vertical hoisting system supplier affects the underground design. The ESIA update was initiated in 2025 because of design optimisations introduced by PowerChina International Group, and updated environmental baseline data collection was completed in early October 2025.
Sector Context
Potash is a key agricultural nutrient, and development projects depend on fiscal stability, infrastructure and large Capital commitments. Mining conventions set fiscal and legal terms between governments and project companies, and changes in national mining laws can raise questions about how existing agreements apply.
Risks Investors Are Watching
The company has said clarity on the Mining Convention is needed for the sale process and financing to proceed, and no sale transaction has been announced. Funding is based on non-binding term sheets, the environmental assessment is paused and cash is limited relative to project capital needs. Shares can move sharply in a session.
What to Watch Ahead
Items cited include formalising the application of the Mining Convention with the Congolese Government, progress of the Formal Sale Process, engagement with OWI-RAMS and the strategic partner, resumption of the ESIA and completion of FEED.
Closing Perspective
Kore Potash’s shares fell in the session, while its latest report described discussions with the Republic of Congo, an ongoing sale process and engineering work at Kola.
_11_27_2026_02_05_18_160634.jpg)