Highlights

  • The Gum Creek Gold Project DFS confirms a 10-year open pit production target of 962,000 ounces at an average mined grade of 1.19 g/t Au, with average production of 98,000 ounces per annum for the first five years.
  • The project has an Ore Reserve Estimate of 18.2 million tonnes at 1.24 g/t Au for 728,000 ounces, constrained to an optimised pit shell.
  • Pre-production Capital is estimated at approximately AUD 350 million including contingency and commissioning, with project finance processes underway and expressions of interest received from Australian and global Mining financiers.
  • A final Investment decision is targeted for Q2 2027, following completion of flora, fauna, and heritage surveys, with first gold production scheduled for the second half of 2028.

Horizon Gold Limited (ASX:HRN) presented its 2026 Annual General Meeting update centred on the Gum Creek Gold Project in Western Australia, following the completion of a Definitive Feasibility Study (DFS) in July 2026. The DFS confirmed the technical and economic case for a large-scale, free-milling open pit gold mine restart, with a ten-year production target of 880,000 recovered ounces derived from an open pit production target of 962,000 mined ounces across 25.1 million tonnes of ore at an average grade of 1.19 g/t Au. The project is located along a significantly underexplored 80-kilometre-long greenstone belt, and Horizon holds a current JORC Mineral Resource of approximately 2.3 million ounces across the broader project area.

DFS Highlights and Mine Plan

The DFS production profile targets average annual gold production of approximately 98,000 ounces for the first five years, with an overall life-of-mine production target of 880,000 recovered ounces across a ten-year mine life. The first five years of production are underpinned by approximately 97% Probable Ore Reserve ounces. The two principal mining areas — the Gidgee Shear Zone and Howards — collectively contribute approximately 78% of the production target by volume, with the remainder drawn from deposits within 48 kilometres of the proposed Gum Creek mill.

The DFS is underpinned by a Probable Ore Reserve of 18.2 million tonnes at 1.24 g/t Au for 728,000 ounces, constrained to an optimised pit shell at an AUD 4,500 per ounce gold price basis for cut-off grade calculations. Pre-production capital is estimated at approximately AUD 350 million. The company has appointed Orimco as project finance advisor and has received expressions of interest from both Australian and global mining financiers. Technical, environmental, and legal independent experts have also been appointed to support the finance process.

Underground and Exploration Upside

The DFS mine plan is confined to the open pit. However, Horizon holds meaningful resources outside the DFS mine plan that represent potential upside to the base case. Free-milling underground resources at Swan, Swift, and Kingfisher deposits total approximately 416,000 ounces at 3.6 g/t Au and sit below or adjacent to the DFS pit design. The Wilsons underground sulphide deposit, which stands at approximately 400,000 ounces at 4.31 g/t Au with 97% in the Indicated category, represents a larger-scale underground opportunity that is currently being studied separately from the open pit programme.

At the Howards deposit, recent RC drilling has extended the mineralised zone by 800 metres to the south and up to 700 metres to the northeast. At Snook, located approximately 24 kilometres north of the Gidgee mill, recent drilling has confirmed resource expansion potential and elevated grades that indicate underground mining potential. Current exploration is also ongoing at the Kingfisher and Swan targets, with historically high-grade intersections providing targets for resource extension drilling.

Development Schedule and Path to FID

An experienced general manager for projects has been appointed, bringing more than 30 years of delivering mining, oil and gas, and energy projects. Tendering has commenced for the accommodation village expansion and for the 2.4 million tonne per annum process plant, with contractor appointment expected in Q2 2027. An existing clearing permit allows for pre-final investment decision works to proceed in advance of the formal approval milestone.

The company is targeting a final investment decision in Q2 2027, subject to the completion of flora, fauna, and heritage surveys and the successful conclusion of the project finance process. First gold production from the restart is scheduled for the second half of 2028. The 80-kilometre project strike remains significantly underexplored, and ongoing drilling is aimed at growing both open pittable and underground resources across the broader Gum Creek system to extend the mine life beyond the current DFS plan.

Key Insights

Gum Creek's DFS is based on a large-scale, free-milling open pit restart with a compelling ore reserve underpinning the first five years of production, reducing the execution risk associated with the early production profile.

The underground and exploration upside — totalling over 800,000 ounces outside the DFS mine plan — represents a material resource inventory that could significantly extend the mine life and add value beyond the current ten-year base case.

The project finance process and FID target of Q2 2027, with first gold in the second half of 2028, provides a clear near-term milestones roadmap against which execution progress can be measured.