Highlights

  • Grange Resources approved the North Pit Underground project, selecting a sub-level cave approach with lower initial Capital than its earlier alternative.
  • September concentrate production increased to approximately 632,000 tonnes, while pellet sales rose to approximately 733,000 tonnes during the quarter.
  • Unit cash operating costs declined to AUD 144.80 per tonne, supported by higher concentrate production and moderate energy prices.
  • Underground development is scheduled for early 2027, with first ore targeted for 2028 and production ramp-up extending to 2030.

Grange Resources Limited (ASX:GRR), operator of the Savage River iron ore mine and Port Latta pellet facilities in Tasmania, traded at AUD 0.103, up 2.50%, on 17 November 2026. Its underground transition now has board Investment approval, while improved quarterly production and lower unit costs support the existing operating base.

Sub-Level Cave Becomes The Approved Pathway

The board announced its final investment decision on 14 October. The selected sub-level cave design has a lower initial funding requirement than the previously studied block cave and is intended to preserve pellet Supply continuity to 2035.

The project’s base-case underground Capital Expenditure is estimated at AUD 287 million, alongside AUD 234 million of sustaining capital over its life. Management projects funding from existing cash reserves and cash generated by open-pit operations.

A possible future block cave remains an option subject to further studies, funding and a separate decision. It should not be combined with the approved development as though both stages were committed.

Quarterly Output Supports The Existing Business

Concentrate production reached 631,649 tonnes in September, compared with 586,906 tonnes in June. Higher weight recovery, which increased from 34.9% to 41.3%, supported the improvement despite maintenance interruptions and periods of harder ore.

Pellet production increased to 604,184 tonnes from 590,883 tonnes. Pellet sales were 732,944 tonnes, compared with 580,239 tonnes in June, drawing on the available production and stockpile position.

The company continued supplying term offtake agreements and spot shipments. These reported operating results provide the immediate cash-generating context for the planned transition underground.

Lower Costs Improve The Quarterly Cash Position

Unit C1 cash operating costs declined to AUD 144.80 per tonne from AUD 157.69. The measure excludes items including royalties, sustaining capital, Depreciation and amortisation, and therefore is not the total cost of production.

The average realised product price increased to AUD 164.41 per tonne, or USD 116.13, free on board Port Latta. The report notes that final pricing settlements typically occur after shipment.

Cash and liquid investments reached AUD 300.41 million at 30 September, compared with AUD 267.90 million at June-end. Trade receivables were AUD 7.82 million. The company also incurred approximately AUD 15.9 million of growth capital expenditure during the quarter.

Development Schedule Sets The Execution Test

Underground development is scheduled to recommence in the first quarter of 2027. The plan targets first sub-level cave ore in 2028 and ramp-up to approximately four million tonnes annually by 2030, while open-pit Mining is expected to finish during 2028.

Environmental approvals for the underground development are in place. Management’s next steps include mining contracts, mobilisation, engineering and workforce planning. The transition still requires delivery against its schedule and capital estimates.

At Southdown in Western Australia, Grange continues seeking suitable Equity investors while maintaining project Assets and approvals. Commodity prices, operating performance, capital costs and the timing of underground development remain material risks. Market Capitalisation was AUD 118.63 million on 17 November, with the shares down 59.80% over one year.