Highlights

  • Coda Minerals has completed an oversubscribed A$6.7 million Placement with institutional and sophisticated investors.
  • Funds will be used to accelerate Pre-Feasibility Study workstreams at the Elizabeth Creek Copper-Cobalt Project.
  • The company expects to hold approximately A$13 million in cash following the Capital raise.
  • Resource, metallurgical and geotechnical drilling programmes have been completed, while several development studies are advancing.
  • Updated Mineral Resource Estimation work is progressing, with completion expected in early July 2026.

Coda Minerals Ltd (ASX:COD) has strengthened its financial position after successfully completing an oversubscribed A$6.7 million placement aimed at accelerating key workstreams associated with the Pre-Feasibility Study (PFS) for its flagship Elizabeth Creek Copper-Cobalt Project in South Australia. The company said the additional capital will support a range of technical, environmental, hydrogeological and approvals-related activities designed to advance the project while bringing forward several important de-risking initiatives.

Shares of Coda Minerals were trading at AUD 0.14 during the afternoon session on 1 June 2026, down 3.33% for the day. Despite the session decline, the stock remains up 81.25% over the past year, reflecting significant gains over the longer term as investors continue to monitor progress at the company's flagship copper development project.

The latest funding initiative comes as Coda advances multiple parallel workstreams at Elizabeth Creek, a 100%-owned copper-cobalt project located within South Australia's Olympic Copper Province. The company views the ongoing PFS as a key stage in demonstrating both the technical and commercial foundations of the project while preparing for future development considerations.

Oversubscribed Placement Strengthens Financial Position

Coda announced that it had secured firm commitments to raise approximately A$6.7 million before costs through a placement to institutional and sophisticated investors.

The capital raising was conducted at an issue price of A$0.13 per new share. Investors participating in the placement will also receive one listed CODO option for every four shares subscribed. These Options carry an exercise price of A$0.15 and are due to expire on 28 March 2029.

According to the company, Demand for the placement exceeded the amount ultimately raised, resulting in an oversubscribed outcome. A total of 51,538,465 new shares were committed under the placement together with 12,884,616 attaching listed options.

Following completion of the raising and associated costs, Coda expects to hold approximately A$13 million in cash, providing additional flexibility as project activities continue to expand.

Management noted that the company entered the raising process with approximately A$7 million already available, indicating that the decision to seek additional capital was aimed primarily at accelerating high-priority work programmes rather than addressing immediate funding requirements.

Funding to Advance Key Pre-Feasibility Study Activities

A major focus of the capital raise is the acceleration of critical PFS workstreams at Elizabeth Creek.

The company outlined plans to direct funding toward expanded metallurgical programmes, additional hydrogeological drilling, approvals-related activities and enhanced independent technical review processes.

Among these initiatives, the expanded metallurgical programme appears particularly significant. Management explained that certain metallurgical test work originally scheduled for later development stages will now be brought forward, allowing technical assumptions to be evaluated earlier in the study process.

By conducting lock-cycle metallurgical testing sooner, the company aims to address key processing questions at an earlier stage and further improve confidence in potential future development pathways.

Coda stated that this approach is intended to enhance the overall quality and robustness of the PFS while supporting ongoing project evaluation efforts.

The company also highlighted the importance of maintaining a strong Balance Sheet while advancing multiple parallel workstreams, noting that financial flexibility remains important as it continues assessing future development, financing and strategic alternatives.

Elizabeth Creek PFS Progresses Across Multiple Fronts

Alongside the financing announcement, Coda provided a comprehensive update on activities underway at Elizabeth Creek.

Several major field programmes have already been completed, including a 19-hole infill and geotechnical drilling programme. Resource, metallurgical and geotechnical drilling campaigns have also now concluded.

The Mineral Resource Estimation update is progressing and is expected to be completed in early July 2026. This update is expected to play an important role in future mine planning activities and broader project studies.

Elsewhere, Stage 1 approvals work in South Australia is approaching completion through the project's Scoping Agreement process.

Additional water drilling activities are expected to commence within the coming weeks, while work on the Tailings Storage Facility study has already begun.

Environmental and ecology surveys have also entered their second phase, reflecting continued progress across permitting and environmental assessment programmes.

Further field activities are scheduled to commence later this month, including LiDAR and aerial survey programmes planned for late June 2026.

Once the updated resource estimate is completed, the company intends to begin integrated mine planning across two proposed open pits and a planned underground operation extending approximately 400 metres below surface.

Collectively, these programmes indicate a significant level of project activity occurring simultaneously as Coda works toward delivery of the PFS.

Why the Expanded Metallurgical Programme Matters

While the funding will support numerous technical initiatives, management placed particular emphasis on metallurgical testing.

According to the company, the expanded programme will accelerate a range of processing studies that otherwise would have been completed during later development phases.

Bringing this work forward enables earlier validation of important processing assumptions and provides an opportunity to evaluate technical risks sooner in the development cycle.

For development-stage Mining projects, metallurgical performance is a critical component of project evaluation because it influences recovery assumptions, processing design considerations and overall development planning.

Coda believes the additional testing will strengthen the technical foundations of the PFS and improve confidence in future project assessment work.

Management indicated that the objective is not only to advance the project timeline but also to enhance the quality of information available during decision-making processes.

Project Scale Continues to Support Development Studies

The Elizabeth Creek Project remains the centrepiece of Coda's development strategy.

According to the resource information referenced in the announcement, the project hosts a combined Mineral Resource of 65.5 million tonnes.

The aggregated resource contains approximately 725,800 tonnes of copper, 33,000 tonnes of cobalt, 28 million ounces of silver and 75,000 tonnes of zinc. The project-wide resource also contains approximately 1.07 million tonnes of copper equivalent metal.

The resource base comprises several deposits including Emmie Bluff, Windabout, MG14 and Cattle Grid South.

The company continues to evaluate these deposits as part of broader mine development studies, with future planning expected to incorporate both open-pit and underground mining scenarios.

The upcoming resource estimate update and integrated mine planning work are expected to provide additional information as the PFS advances.

Placement Structure and Next Steps

The placement was led by Cumulus Wealth and Leeuwin Wealth, which acted as Joint Lead Managers.

Of the total shares being issued, a portion will be issued under the company's existing placement capacity, while the remaining securities and attaching options will require Shareholder approval at an upcoming general meeting.

Directors also participated in the raising, subscribing for 1,153,846 shares and 288,461 attaching options, subject to shareholder approval.

Settlement of the first Tranche is expected to occur on or around 4 June 2026.

The issue price of A$0.13 per share represented a discount to both the company's recent trading price and its 15-day Volume weighted average price prior to the announcement.

With funding secured and multiple technical programmes underway, management expects project activity and associated news flow to increase over the coming months as Elizabeth Creek advances through the PFS stage.

What This Means for Investors

Coda Minerals' latest announcement centres on strengthening its balance sheet while accelerating development work at the Elizabeth Creek Copper-Cobalt Project.

The oversubscribed A$6.7 million placement provides the company with an expected cash position of approximately A$13 million and allows several important technical programmes to be brought forward. These include expanded metallurgical testing, hydrogeological drilling, environmental studies, approvals work and resource modelling activities.

At the same time, numerous project milestones continue to progress, including completion of major drilling campaigns, advancement of the updated Mineral Resource Estimation and the commencement of additional engineering and environmental studies.

As the company moves toward delivery of its Pre-Feasibility Study, investors are likely to monitor upcoming milestones, particularly the resource update expected in early July and the results of ongoing technical workstreams across the Elizabeth Creek Project.