Key Highlights
- Norwest Minerals (ASX:NWM) assessed a standalone open-pit mine and on-site heap leach operation at its wholly owned Bulgera Gold Project.
- The schedule models approximately 87,000 ounces of recovered gold over 57 months of operations at Bulgera in Western Australia.
- Roughly 78% of the processed material in the production target is classified as Indicated and 22% as Inferred.
- The study estimates A$54 million in pre-production Capital and proposes starting prefeasibility work in January 2027, subject to funding.
Norwest Minerals (ASX:NWM) is evaluating the development of its wholly owned Bulgera Gold Project in Western Australia. A 23 November scoping study examined open-pit Mining and processing oxidised material on site. It sets out a preliminary mine schedule, plant capacity and capital requirements, alongside drilling and metallurgical work proposed for the next study.
The material included in the Bulgera mine plan
Bulgera is in the Plutonic Well Greenstone Belt, approximately 200 kilometres north of Meekatharra and 50 kilometres northeast of the Plutonic Gold Mine. The study models mining 6.3 million tonnes of highly and moderately weathered oxide material at an average diluted grade of 0.57 grams of gold per tonne. It assumes a waste-to-ore strip ratio of 3.1 to one.
The preliminary schedule covers 57 months of operations and estimates approximately 87,000 ounces of recovered gold, equivalent to about 18,000 ounces a year on average. The nominal processing rate is 1.5 million tonnes a year. Norwest said the production target draws 78% of its processed material from Indicated Mineral Resources and 22% from Inferred Mineral Resources. It put the Indicated share at about 84% during the first 12 quarters of processing.
How the study models gold recovery and capital
The design uses conventional heap leaching. Under that approach, crushed material is stacked on a prepared pad and treated with a solution to recover gold. Norwest modelled a 25-millimetre crush size and weighted average field recovery of about 74% to 75%. The field recovery is a study assumption informed by metallurgical test work. The company plans to test finer crushing on moderately weathered material during prefeasibility.
Laboratory column tests on Price deposit samples returned 80% extraction for highly weathered oxide over 73 days and 78% for moderately weathered oxide over 98 days. Norwest used lower recovery estimates for the field design, allowing for factors such as compaction, solution flow and the length of a commercial leach cycle. The study’s base schedule uses a weighted blend of both oxide types.
Pre-production capital is estimated at A$54 million, including A$3 million in contingency. It covers crushing equipment, processing facilities, first-stage heap leach earthworks and site infrastructure. Norwest estimated a maximum cash drawdown of roughly A$62 million and a further A$6 million of staged sustaining and expansion spending across years two and three. Funding availability remains an assumption of the scoping work.
What the next study would investigate
Subject to funding, Norwest plans to begin prefeasibility work in January 2027 and finish in December 2027. It has identified the Price Pit for infill drilling, where 38% of the pit inventory is currently Inferred. It plans further tests on fresh rock excluded from the current mine plan and to sample historical waste dumps and backfill for potential processing material.
The company also identified geotechnical drilling, groundwater assessment, waste geochemistry and flood modelling for Bulgera Creek. Norwest intends to discuss financing while that work progresses. The scoping study uses preliminary assessments, and further exploration and evaluation would be needed before Ore Reserves can be estimated.
Key Insights
Bulgera’s study sets out a standalone processing option with a preliminary mine schedule and capital requirements. The next program would address grade confidence, recovery and site design. Part of the production target relies on Inferred Resources, which carry lower geological confidence than Indicated Resources. The proposed 2027 timetable remains subject to funding.