Highlights

  • Boss Energy (ASX:BOE) reported Honeymoon drummed production of 359,335 lbs U3O8 for the September 2026 quarter.
  • The New Feasibility Study outlines about 13.8 Mlbs of drummed U3O8 over nine years under a wide-spaced wellfield design.
  • FY27 guidance is production of 1.25 to 1.30 Mlbs at an All-In Sustaining Cost of A$83 to A$92 per lb.
  • Total cash and Liquid assets were A$194.9 million at 30 September 2026, with no debt.

Boss Energy Limited (ASX:BOE) is a uranium producer whose principal asset is the Honeymoon in-situ recovery operation in South Australia, alongside a 30% interest in the Alta Mesa project in Texas. In the 24 November 2026 session, shares in the company were priced at AUD 1.35, a gain of 3.05%. Recent company disclosures covered Honeymoon production and costs, a New Feasibility Study, FY27 guidance and a change of chair.

Honeymoon and Alta Mesa: Business Overview

Honeymoon uses in-situ recovery, in which uranium is dissolved underground and pumped to a processing plant for ion exchange and drumming of triuranium octoxide (U3O8). The site ran six wellfields and five ion exchange columns during the September 2026 quarter. Alta Mesa is a South Texas in-situ recovery project in which Boss holds 30%, with enCore holding 70%. The company is also assessing nearby deposits, including Jason's Deposit and Gould's Dam, as potential sources of future feed for the Honeymoon plant.

September 2026 Quarter: Production, Sales and Costs

In late October 2026, ASX:BOE released its September quarterly report. Honeymoon drummed production was 359,335 lbs of U3O8, 0.8% below the previous quarter, while ion exchange production was 337,093 lbs. Ion exchange flow reached a record 3.69 million cubic metres and recovery was 95.7%. Pregnant leach solution tenor fell 12.6% to 43 mg/L, and rainfall caused 19 lost production days in August.

C1 cost was A$47 per lb and all-in sustaining cost was A$79 per lb. Capital Expenditure totalled A$13 million, of which A$9 million was sustaining. Sales were 300,621 lbs for A$35.2 million, at an average realised price of A$117.0 per lb, up 9%. Alta Mesa produced 10,000 lbs on a 100% basis, and Boss received no product for the quarter. The company attributed the decline to Texas permitting delays for new wellfields.

New Feasibility Study and Regional Hub Aspiration

The New Feasibility Study was delivered ahead of schedule and supports a wide-spaced wellfield design. It outlines life-of-mine production of about 13.8 Mlbs of drummed U3O8 over nine years, with economic production forecast until at least FY34. The wider spacing is forecast to lower life-of-mine all-in sustaining cost by about A$30 per lb compared with the original spacing on the updated resource. Inferred resources make up 35% of the production target, while the first four years are 89% Indicated.

Separately, ASX:BOE described an aspiration to process ore from Honeymoon, Jason's Deposit and Gould's Dam through the Honeymoon plant, at 2.5 Mlbs per year and an all-in sustaining cost of A$65 per lb by the early 2030s. The company states this is not a production target and that it does not yet have reasonable grounds to expect it. Peter Botten became Chair on 30 September 2026, with Wyatt Buck remaining as a Non-Executive Director.

Financial Position and Uranium Sector Context

At 30 September 2026, cash on hand was A$39.2 million, investments and liquid assets were A$31.4 million, and inventory was valued at A$124.2 million, or 1,641 klbs. Total cash and liquid assets were A$194.9 million, down A$12.4 million over the quarter, and the company reported no debt. The realised price for the December 2026 quarter is expected at about US$87 to US$89 per lb, with legacy contract deliveries of 124 klbs expected in each of the March and June 2027 quarters.

FY27 guidance sets production at 1.25 to 1.30 Mlbs, C1 cost at A$51 to A$56 per lb, all-in sustaining cost at A$83 to A$92 per lb and capital expenditure at A$58 million to A$65 million. For uranium producers using in-situ recovery, wellfield performance, weather, reagent use and contract timing all influence reported output and unit costs.

Risks to Consider

For ASX:BOE, the wide-spaced wellfield design is still being tested at scale, and wellfield tenor is declining. Weather disruption affected August 2026, and the company's safety rate remains above its target after two lost time injuries in the quarter. At Alta Mesa, new wellfield production depends on Texas permits. Approvals for satellite deposits, the share of Inferred resources in the production target and the unproven steps behind the regional hub aspiration add further uncertainty.

What to Watch Next

In the December 2026 quarter, ASX:BOE expects final flushing data and first leaching results from the EKT1 wellfield, an Environment Protection and Biodiversity Conservation Act decision on the Honeymoon Mine Extension, and the PAA3 Extension permit at Alta Mesa. HMT1 wellfield production and the PAA8 permit are due in the March 2027 quarter. Drilling at Jason's Deposit, with 137 mud rotary holes planned for resource delineation, is expected to report by the June 2027 quarter.

Key Insights

Boss Energy (ASX:BOE) delivered steady Honeymoon output in the September 2026 quarter, completed its New Feasibility Study and set FY27 guidance. The Balance Sheet shows no Debt and A$194.9 million in cash, investments and inventory. For ASX:BOE, wellfield tenor, permitting at Alta Mesa and delivery of the guided cost range are the measures most directly tied to results in coming quarters.