Highlights
- 29Metals (ASX:29M) produced 4.2kt of copper at Golden Grove.
- September-quarter gross Revenue declined to AUD 94.1 million.
- Group Liquidity was AUD 142 million at September quarter-end.
- Capricorn Copper restart planning depends on tailings approvals.
29Metals Limited (ASX:29M) mines copper and other metals in Australia, with Golden Grove in Western Australia operating alongside the currently suspended Capricorn Copper operation in Queensland. Its shares ended 13 November 2026 at AUD 0.255. The October September-quarter update detailed lower metal production after planned maintenance, continued development of new Golden Grove ore sources and regulatory steps affecting the potential restart of Capricorn Copper.
Copper and Zinc Operations
Golden Grove produces copper, zinc and precious-metal by-products from several underground ore sources. The mine depends on coordinated underground development, ore blending, processing and concentrate sales. Capricorn Copper remains outside normal production while restart work advances. The difference between a producing mine and a project awaiting approvals is material when considering near-term cash generation and future Capital commitments.
At Golden Grove, new Mining areas are being developed to improve production flexibility. Xantho Extended is an important copper and zinc source; Gossan Valley and Oizon are additional underground development projects. The timing of access to these ore bodies affects available feed grades, mine sequencing and how much ore can be processed in a given quarter.
September Production and Development Work
Golden Grove copper output was 4,200 tonnes in the September 2026 quarter, versus 4,800 tonnes in June. Zinc production fell to 2,000 tonnes from 3,100 tonnes. The company completed a planned 11-day maintenance shutdown, while ore milled decreased to 301,000 tonnes from 363,000 tonnes. Ore mined increased 17% to 351,000 tonnes from 299,000 tonnes, reflecting activity in other mining areas during Xantho’s suspension.
Mining recommenced at Xantho Extended in October. Gossan Valley remained scheduled for first ore by the end of 2026, while Oizon delivered first development ore during the September period and was also expected to begin production by year-end. These additions may change the available ore mix, but production volumes and grades will need to be demonstrated through subsequent operating reports.
Revenue, Liquidity and Cost Pressures
The group reported September-quarter gross revenue of AUD 94.1 million, compared with AUD 164.4 million in the preceding quarter. Lower sales volumes were the principal driver. Golden Grove C1 cost was US$5.24 per pound of copper sold, against US$4.64 in June, as lower sales volumes increased unit costs. Quarterly gross revenue and cost metrics differ from audited statutory profit measures.
At 30 September, cash and cash equivalents were AUD 128 million, down from AUD 188 million at 30 June. Group liquidity declined to AUD 142 million from AUD 202 million, while the company moved from AUD 22 million net cash to AUD 31 million net debt. The quarterly cash movement reflected reduced operating inflows and higher Investment in mine development.
Copper prices, zinc by-product contributions and currency movements affect the Economics of production. Interruptions to the mining schedule or lower feed grades can affect output even when metal prices are favourable. The group maintained its 2026 guidance and anticipated increased mining and processing volumes in the December quarter, supported by the resumption of Xantho Extended activity.
Capricorn Copper and Forward Risks
At Capricorn Copper, water levels had been reduced sufficiently that they were no longer identified as a barrier to restart. However, approval for Tailings Storage Facility 3 remained a critical prerequisite. The restart definitive feasibility study was on track for completion by the end of 2026, with a final investment decision contingent on approvals and funding considerations.
29Metals (ASX:29M) was evaluating alternatives for financing Capricorn Copper while allocating funds to Golden Grove. Execution risk remains at both assets: development timing, tailings approvals, metal prices and available liquidity can influence schedules and capital needs. Investors may track the next quarter’s sales volumes, costs and progress at Gossan Valley and Oizon.
Key Insights
29Metals reported lower September-quarter output, revenue and liquidity while completing maintenance and advancing additional ore sources. Golden Grove’s production recovery and Capricorn Copper’s regulatory pathway are separate but related priorities for the group’s operating and financing decisions.