Highlights
- 29Metals (ASX:29M) produced 4.2 thousand tonnes of copper at Golden Grove in the September 2026 quarter, against 4.8 thousand tonnes in June.
- An 11-day planned maintenance shutdown affected milling and sales, while quarterly ore mined increased to 351 thousand tonnes.
- Group Liquidity declined to AUD 142 million at 30 September 2026 from AUD 202 million three months earlier.
- Golden Grove maintained 2026 guidance as work advanced at Xantho Extended, Gossan Valley and Oizon alongside Capricorn Copper restart planning.
29Metals (ASX:29M) is a copper-focused base and precious metals producer with Australian Mining Assets and exploration interests. During trading on 23 November 2026, its shares were quoted at AUD 0.235, showing a 0.00% change at the time of writing while the market remained open. Recent operating disclosures centre on Golden Grove production, new ore sources and progress towards a potential Capricorn Copper restart.
Golden Grove: Mining Activity and New Ore Sources
Golden Grove in Western Australia is the group’s operating mining asset, producing copper, zinc and precious metals from underground deposits. The September quarter included a planned 11-day maintenance shutdown. Although ore mined rose 17% from the June quarter to 351 thousand tonnes, ore milled declined to 301 thousand tonnes from 363 thousand tonnes. Copper output consequently fell to 4.2 thousand tonnes from 4.8 thousand tonnes, while zinc production declined to 2.0 thousand tonnes from 3.1 thousand tonnes.
September-Quarter Revenue, Costs and Liquidity
29Metals (ASX:29M) recorded gross Revenue of AUD 94.1 million for the September quarter, compared with AUD 164.4 million in June. Copper contributed AUD 79.2 million, while gold and silver contributed AUD 9.5 million and AUD 5.9 million respectively. Payable copper sales declined to 8.1 million pounds from 11.5 million pounds. The lower metal sales volumes reflected the maintenance period and operational scheduling rather than a stated change in the company’s production guidance.
At 30 September 2026, unaudited cash and cash equivalents were AUD 128 million, compared with AUD 188 million at 30 June. Group liquidity decreased from AUD 202 million to AUD 142 million, and unaudited net Debt stood at AUD 31 million versus net cash of AUD 22 million at June-end. Higher project Investment and reduced Operating Cash Flow both affected the quarter. Management stated that available liquidity was sufficient for its identified Golden Grove development commitments.
Capricorn Copper Restart: Approvals and Funding
Capricorn Copper in Queensland remains outside production while restart preparations continue. The company reported that reduced mine water levels were no longer an impediment to restarting operations. However, approval for the proposed third tailings storage Facility remained a critical dependency. During September, 29Metals submitted a response to the regulator’s request for information relating to that facility.
Risks and Uncertainties to Watch
29Metals (ASX:29M) faces operating risks linked to mine sequencing, ore grades, processing reliability and production ramp-up at Golden Grove. Lower sales can increase unit costs, while labour, power, diesel and consumables remain relevant cost exposures. At Capricorn Copper, environmental approvals, engineering requirements, funding terms and the eventual restart timetable create separate uncertainties. Copper and by-product prices can influence revenue independently of physical production.
What to Watch Next
The next quarterly update can confirm whether Xantho Extended ramped up as planned and whether Gossan Valley and Oizon achieved their initial ore milestones. Subsequent reporting should also show whether higher mine throughput converted into greater sales, reduced unit costs and improved cash flow. At Capricorn Copper, the feasibility study, tailings approval process and any binding funding arrangements are the principal identifiable decision points.
Key Insights
29Metals (ASX:29M) entered the final quarter of 2026 with maintained production guidance but lower September-quarter revenue and liquidity. Golden Grove development work provides p