Highlights

  • 29Metals received preliminary approval for Capricorn Copper’s environmental authority amendment covering a new tailings Facility and associated restart infrastructure.
  • The decision includes a twenty-business-day objection period, while a federal environmental process remains a separate approval requirement before restart.
  • Golden Grove mined 156,000 tonnes in October, its highest monthly Volume in more than three years following additional ore contributions.
  • Capricorn Copper’s feasibility study remains targeted for year-end, with financing alternatives under evaluation before a final restart Investment decision.

29Metals Limited (ASX:29M), which operates Golden Grove and is evaluating a Capricorn Copper restart, received preliminary Queensland approval for new tailings infrastructure on 17 November 2026. It also reported improved October Mining performance. Shares traded at AUD 0.275, up 7.84%, that day, while federal clearance, financing and a restart investment decision remained outstanding.

Preliminary Approval Advances Tailings Infrastructure

The Queensland environmental authority amendment provides for Tailings Storage Facility 3 and associated infrastructure at Capricorn Copper. The department also issued a referral notice allowing eligible Stakeholders a twenty-business-day objection period, during which the matter may be referred to the Land Court.

The new facility is intended to provide a long-term tailings solution. A water treatment plant forms another part of the proposed restart infrastructure, with detailed designs being finalised and construction tenders expected in 2027.

The preliminary decision advances the approval pathway but does not mean operations have restarted. The objection process and remaining environmental requirements remain relevant conditions.

Federal Process And Financing Remain Separate

29Metals expects to respond before year-end to a federal information request under the Environment Protection and Biodiversity Conservation referral process. The company identified this as the final approval process required to enable a restart.

The restart definitive feasibility study, incorporating the tailings facility and water treatment plant, remains targeted for completion by the end of 2026. Funding Options include streaming, Royalty and joint-venture proposals.

These workstreams support a potential final investment decision. Receiving proposals or preliminary state approval does not establish a completed funding package or an unconditional construction commitment.

Surface water inventory has been reduced by 2.3 gigalitres since operations were suspended in March 2024. Levels are now below both the maximum operating level and the environmental authority’s design storage allowance compliance level.

Golden Grove Mining Improves In October

Golden Grove mined 156,000 tonnes in October, its highest monthly volume in more than three years. September mining had reached 148,000 tonnes, with October benefiting from additional Gossan Hill ore sources and the restart of Xantho Extended.

The second Xantho Extended stope firing commenced on 15 November. Access and bypass development continued, while the expanded seismic monitoring system recorded an initial response consistent with expectations.

Mill performance improved following September’s eleven-day maintenance shutdown. Higher availability and throughput, supported by run-of-mine stocks, produced an annualised October processing rate of 1.6 million tonnes. This is a monthly run-rate measure rather than completed annual production.

New Ore Sources Support The Next Stage

The November update retained expectations for first production from Oizon and first development ore from Gossan Valley before year-end. Their progression remains important to mine-plan flexibility and production consistency.

The September report recorded 4,200 tonnes of copper and 2,000 tonnes of zinc production, with group Liquidity of AUD 142 million at quarter-end. These are historical quarterly measures, distinct from October’s operating improvements.

Regulatory timing, mine execution, metal prices and financing terms remain relevant risks. Market Capitalisation was AUD 481.27 million on 17 November 2026, while the shares were down 31.57% over one year.