Highlights
- PDI Gold received Guinea exploitation permits for Bankan and Mansounia in November 2026.
- September-quarter gold poured totalled 52,865 ounces, below June’s 64,026 ounces.
- Group September-quarter Revenue reached US$282.9 million, with 66,928 ounces sold.
- PDI maintained calendar 2026 guidance of 198,000–220,000 ounces poured.
PDI Gold Limited (ASX:PDI) operates the Kiniéro gold mine in Guinea and the Nampala mine in Mali, while developing the Bankan project in Guinea. On 17 November 2026, Guinea granted exploitation permits for Bankan and the Mansounia deposit at Kiniéro. Construction costs and scheduling remain important.
Bankan Approval Changes the Development Sequence
The Bankan permit covers 98.6 square kilometres for an initial 15-year term. Under Guinea’s Mining Code, the government is entitled to a 15% interest in the permits. PDI (ASX:PDI) plans to accelerate engineering, procurement and compensation work.
Bankan’s definitive feasibility study outlined average annual output of approximately 250,000 ounces over more than 12 years and estimated upfront Capital Expenditure of US$463 million. The company expects first gold in mid-2028 and intends to publish an optimised implementation schedule, capital estimate and production profile in early 2027. An updated cost estimate remains outstanding.
Kiniéro Output Leads the Operating Portfolio
PDI (ASX:PDI) poured 52,865 ounces during the September 2026 quarter, down 17% from 64,026 ounces in June. Kiniéro contributed 45,599 ounces, compared with 54,252 ounces previously, while its processing plant milled 2.28 million tonnes, up 3%. The average grade declined from 0.86 to 0.69 grams per tonne and recovery moved from 90.5% to 88.3%, contributing to lower output despite maintained processing activity.
Kiniéro sold 61,149 ounces in September, including bullion produced in the preceding quarter. Its All-In Sustaining Cost was US$1,246 per ounce, against US$1,254 in June. Sales include previously produced bullion. PDI (ASX:PDI) continues to rely on Kiniéro for most group production while Bankan advances.
Nampala Costs Contrast With Higher Group Sales
Nampala poured 7,266 ounces in September, compared with 9,774 ounces in June. The mine’s all-in sustaining cost reached US$2,914 per ounce, substantially above Kiniéro’s cost, as pit cutback work affected ore access. Group sales nonetheless increased 37% to 66,928 ounces, and revenue rose 30% from US$217.3 million to US$282.9 million. Group all-in sustaining costs decreased slightly to US$1,390 per ounce from US$1,408.
Cash and bullion totalled US$404.6 million at 30 September, versus US$364.3 million at 30 June. The September balance included US$81.5 million of restricted cash and US$39.5 million of bullion. PDI (ASX:PDI) is working to improve Nampala output.
Guidance and Execution Milestones
The group maintained calendar 2026 guidance of 198,000–220,000 ounces poured, with 165,068 ounces reported for the first nine months. The December quarter will establish the full-year outcome. For Bankan, detailed engineering was approximately 20% complete at the September-quarter update, and mechanical equipment procurement was substantially complete. The revised budget and construction progress remain important.
The group’s stated objective is to exceed 400,000 ounces of annual production by 2029 once Bankan is operating. PDI (ASX:PDI) must manage development expenditure, mining costs and Guinea and Mali regulatory requirements while delivering from its existing operations.
Key Insights
Bankan and Mansounia permits mark a change in PDI Gold’s development position. September sales and cash holdings increased, while poured ounces declined and Nampala costs rose. The next measurable milestones are full-year production against guidance, an updated Bankan capital and schedule assessment, and evidence that construction preparations translate into execution.