Highlights
- Plant IV has completed all civil construction activities during Q1 FY27.
- The company has installed and completed dry runs for all seven production machines.
- Trial production is expected to be completed within the next few weeks, according to the operational update.
- Commercial production at the new facility is targeted to commence in October 2026.
- Upon stabilization, Plant IV is expected to increase steel fiber manufacturing capacity from 300 MT per month to approximately 800 MT per month.
Plant IV Marks a Key Milestone in Manufacturing Expansion
Kasturi Metal Composite Limited (KMCL) has shared significant progress on its upcoming Plant IV as part of its Q1 FY27 operational business update. The company stated that the new manufacturing facility has reached several important construction and installation milestones, representing a notable step in its ongoing capacity expansion programme.
According to the company, the operational update is intended to keep shareholders informed about business developments and should not be considered a substitute for its financial results, which will be disclosed separately.
Civil Construction and Equipment Installation Completed
The operational update states that all civil construction activities at Plant IV have been completed. During the quarter, the company also completed the installation and dry run of all seven production machines planned for the facility.
These milestones indicate that the project has progressed beyond the construction phase and has entered the commissioning stage. Completion of machine installation is an important operational step before commercial manufacturing activities can begin.
The company has not disclosed any changes to the planned configuration of the facility or additional capital expenditure related to the project.
Trial Production Expected Before Commercial Operations
Following the completion of construction and equipment installation, Kasturi Metal Composite has indicated that trial production is expected to be completed within the next three weeks.
Trial production allows manufacturers to test production lines, validate equipment performance and fine-tune operational processes before beginning commercial manufacturing.
According to the operational update, commercial production at Plant IV is targeted to commence during October 2026. The filing does not provide further details regarding production ramp-up schedules or utilisation levels beyond the commencement target.
Capacity Expansion Could Enhance Manufacturing Capability
One of the most significant aspects of Plant IV is the planned increase in installed steel fiber manufacturing capacity.
The company stated that, once the facility stabilises, installed manufacturing capacity is expected to increase from the existing 300 MT per month to approximately 800 MT per month.
This represents a substantial increase in production capability and reflects the company's continued focus on expanding its manufacturing infrastructure. However, the operational update does not provide guidance regarding expected production volumes, utilisation rates or future revenue contribution from the additional capacity.
Expansion Supports Long-Term Manufacturing Strategy
Manufacturing capacity expansion forms one part of Kasturi Metal Composite's broader operational initiatives during Q1 FY27. Alongside Plant IV, the company also reported progress in exports, product innovation and business development activities across domestic and international markets.
While Plant IV is expected to enhance production capability after stabilisation, the company has not disclosed any revised financial projections linked specifically to the new facility.
Future updates relating to production performance and operational utilisation are likely to be communicated through subsequent regulatory disclosures where applicable.
Company Continues to Focus on Operational Development
The latest operational business update indicates that Kasturi Metal Composite continues to invest in manufacturing infrastructure while advancing product development and market expansion initiatives.
The completion of construction activities and installation of production machinery places Plant IV in the final stages before commercial operations. As outlined by the company, commercial production remains targeted for October 2026, subject to completion of trial production and project stabilisation.
The operational update does not include any revised financial outlook or earnings guidance associated with the expansion project.

Data Source: Company Filings; Analysis: Kalkine Group
Conclusion
Kasturi Metal Composite's Plant IV has reached several important milestones, including completion of civil construction, installation of all seven production machines and commencement of the trial production phase. According to the company, commercial production is targeted for October 2026, with installed steel fiber manufacturing capacity expected to increase from 300 MT per month to approximately 800 MT per month once the facility stabilises. The announcement reflects continued progress in the company's manufacturing expansion while remaining separate from its financial disclosures.