Key Highlights

  • Lithium Universe (ASX:LU7) completed a prefeasibility study for a proposed battery-grade lithium carbonate refinery at Brownsville, Texas.
  • The study modelled annual output of up to 18,270 tonnes and estimated Capital costs at approximately US$607 million.
  • A binding ten-year agreement with Norah Mining would cover about 60% of planned long-term spodumene requirements, subject to commissioning.
  • Lithium Universe completed an A$900,000 Placement and separately reported laboratory results from its electronics recycling research program.

Lithium Universe (ASX:LU7) is developing lithium refining projects and recycling technologies. Its September Quarterly Report outlined a prefeasibility study for a proposed Texas refinery, including the design, equipment scale and approach to buying feedstock. The report also covered laboratory research, a share placement and management changes.

Brownsville’s planned output and design

The study modelled a plant that could produce up to 18,270 tonnes of battery-grade lithium carbonate each year. Lithium Universe based the design on the process used at the Jiangsu Lithium Carbonate Refinery, adapting it to a modular plant at Brownsville. In the published study, estimated Capital Expenditure was approximately US$607 million, including a US$130 million contingency.

The proposed location has deep-water access for shipments of spodumene concentrate, the feedstock selected for conversion into lithium carbonate. The company identified Africa, Brazil and North America as potential sources for feedstock. Brownsville was at the prefeasibility stage when the quarterly report was issued. Planned next steps included a definitive feasibility study, engineering work, securing a long-term site Lease and advancing permitting and site investigations.

Norah offtake and the remaining supply

Lithium Universe disclosed a binding ten-year offtake agreement with Norah Mining in Nigeria. The contracted Volume represents about 60% of projected long-term spodumene needs for the proposed refinery, subject to successful commissioning by Norah. The agreement includes a 7.5% discount to prevailing market prices. The quarterly report described the agreement as one source of future feedstock for Brownsville.

Lithium Universe envisaged sourcing the remaining concentrate from other producers. The quarterly report listed finalising longer-term Supply arrangements and progressing project financing and Partnership discussions as further steps. The study used a long-term spodumene concentrate price of US$1,170 per tonne and a battery-grade lithium carbonate price of US$20,970 per tonne. These were inputs to its model for the proposed facility.

The company’s model estimated operating costs, excluding spodumene, at about US$3,566 per tonne of lithium carbonate. The supply contract addresses a portion of the excluded input. The company also said it planned to discuss a long-term site lease with the Port of Brownsville as part of the next phase.

Recycling research and corporate financing

Tests at the University of Edinburgh addressed gallium and platinum recovery from electronic waste. Lithium Universe reported gallium recovery above 99% in controlled laboratory conditions and approximately 99% to 100% for platinum. It separately announced a research project involving Macquarie University and CSIRO to advance a microwave process for separating materials in solar panels. The two research streams cover different feedstocks.

Lithium Universe raised A$900,000 at A$0.0035 per share through two placement tranches, with one free option per two shares. Its Cash Flow report recorded A$429,000 of closing cash and A$522,000 of net operating cash outflow for the September quarter. The company also disclosed the departures of its chief executive and chief technology officer and said it had started a search for a new chief executive.

The steps between study and construction

The Brownsville study set out a design capacity and capital estimate, with a conditional supply arrangement covering part of the proposed feedstock requirement. Engineering, leasing, permitting and financing remained on the company’s work list. Its laboratory recycling results were reported as separate research milestones, with further work needed before any scale-up could be assessed.