Key Highlights

  • Metallium (ASX:MTM) received an initial USD 500,000 payment under a 12-month technology-services agreement.
  • Three flash joule heating reactors operated in parallel during a 12-hour commissioning campaign.
  • Binding contracts covered approximately 4,000 tonnes of annual circuit board feedstock.
  • Metallium held AUD 50.7 million in cash and cash equivalents at 30 September 2026.

Metallium (ASX:MTM), a metals processing technology developer, advanced work on a circuit board processing plan for its Gator Point campus in Texas in the September 2026 quarter. In its 30 October filing, the company reported preliminary recovery results, a multi-reactor test using a separate feedstock and the first receipts from a technology-services contract.

Circuit board processing at Gator Point

Printed circuit board processing remained the company’s near-term commercial priority. The initial planning basis was approximately 8,000 tonnes a year. Existing binding feedstock Supply contracts covered about half that volume. The company was preparing an implementation plan for standalone modules, each designed around processing 8,000 tonnes a year. The plan would address equipment purchases, the order of commissioning steps and potential Revenue across different metal grades in the incoming material.

Metallium had advanced process design, equipment selection and the identification of product streams it intended to sell. Preliminary batch pre-processing tests indicated recoveries above 90% for copper, gold, silver, tin and palladium into mixed metal-bearing streams. Further testing and work to reconcile those results were continuing, along with efforts to secure Patent protection for the process. Publication of the implementation plan was subject to technical and commercial review and board approval.

On site, Metallium secured extra land north of the campus to meet a separation-distance requirement affecting relocated test facilities. The company said that step allowed commissioning involving chlorination to resume. It had obtained approvals and completed civil works for a power upgrade, while work on fire protection and utilities continued.

Three-reactor campaign and services receipts

The company used catalytic converter feedstock containing platinum group metals in its three-reactor campaign. The reactors ran in parallel for 12 hours, taking the platform from commissioning with inert material into reactive processing. Metallium said it would use the resulting data to refine reactor configuration, feed preparation and operating conditions. The campaign was a commissioning step on a different feedstock from the circuit boards covered in the implementation plan.

Metallium received its first technology-services payment from Environmental Clean Technologies under a 12-month agreement covering MXene technology. The company reported producing MXene in the initial two runs on its flash joule heating platform after signing the agreement. Its Texas Subsidiary also completed USD 250,000 of paid work during the quarter in support of US government contracts and technology development.

Cash position and proposed financing

The Appendix 4C reported AUD 6.5 million of net cash used in Operating Activities for the quarter. Metallium was evaluating equipment finance, Working Capital facilities and potential customer prepayments linked to offtake to support development in stages. Those funding avenues were presented as Options under consideration in the October filing.

After quarter-end, Metallium signed a non-binding memorandum of understanding with Commodity trader Traxys. The framework provided for an evaluation of feedstock sourcing, tolling, offtake, hedging, prepayment and possible strategic Investment structures. A commercial agreement would require further steps. The company identified financing and procurement as part of its plan to build out the site in phases.

Timing for circuit board products

The quarterly filing anticipated initial revenue from circuit board metal products in the first half of calendar 2027 and a staged production ramp-up from the second half. Metallium said intermediate metal-bearing products could be produced earlier, subject to deployment of the process, commissioning and product requirements. The company linked the timing to the planned installation of equipment, additional test work and qualification of Downstream products at Gator Point.