Highlights

  • Tungsten Mining (ASX:TGN) published a Watershed definitive feasibility study in November 2026 ahead of a targeted Investment decision.
  • The study described a probable reserve of 36.6 million tonnes grading 0.124% tungsten trioxide.
  • Pre-production project Capital was estimated at AUD 264.4 million, including amounts already spent or committed.
  • The Watershed schedule targeted mining in April 2027 and first concentrate production in June 2027, subject to execution.

Tungsten Mining (ASX:TGN) is developing tungsten projects in Australia, led by Watershed in Far North Queensland. Its November 2026 definitive feasibility study outlined mine economics, Capital Expenditure and expected production timing. Financial model outputs depend on Commodity prices and project assumptions, while an investment decision requires consideration of the remaining funding and commercial arrangements.

Watershed Study Economics and Ore Reserve

The Watershed project is located approximately 130 kilometres north of Cairns. Its November definitive feasibility study reported a pre-tax net present value of AUD 1.57 billion and a pre-tax internal rate of return of 70%, using the study assumptions. These are modelled outputs, not realised project returns.

The study used a long-term ammonium paratungstate assumption of US$1,500 per metric tonne unit. It also showed sensitivity to alternative price scenarios, reinforcing that commodity assumptions can materially affect modelled valuations. The estimated C1 cash cost was US$440 per unit and All-In Sustaining Cost US$538 per unit.

The plan is an open-pit mine with a probable ore reserve of 36.6 million tonnes at 0.124% tungsten trioxide. About 10% of planned production relies on inferred material outside the reserve. The company is targeting the start of mining in April 2027 and first concentrate in June 2027.

Capital Requirements and Financing Process

Pre-production capital was estimated at AUD 264.4 million, of which AUD 57.8 million had already been spent or committed, leaving AUD 206.6 million to be spent from November. The peak funding requirement was put at AUD 277 million, with about AUD 255 million still to be secured.

Tungsten Mining reported AUD 70.1 million cash at 30 September, following an Equity placement. The Quarterly Report described non-binding lender proposals, including gearing scenarios of up to approximately 70%. No binding project offtake was reported as completed when the feasibility study was released.

Mt Mulgine Development Context

Beyond Watershed, the company owns the Mt Mulgine tungsten project in Western Australia. Its September quarter report described a pre-feasibility study for an eight million tonne a year operation over 21 years, with estimated initial capital of AUD 870 million. That is a much larger and longer-dated undertaking than Watershed.

Mt Mulgine is a separate Western Australian development concept and should not be merged with Watershed’s feasibility metrics. Its estimated scope and longer project horizon entail their own engineering and financing requirements.

The September-quarter account described Mt Mulgine as a much larger, longer-term proposition than Watershed. Its eight-million-tonne-a-year study concept extends over a potential 21-year operating period.

Commodity Assumptions and Investment Timetable

Tungsten project economics are exposed to product prices, construction expenditure, delivery timing and financing terms. The study is forward-looking, while Debt arrangements and offtake terms remain to be secured. A targeted investment decision is not equivalent to an approved commitment to build.

The Annual General Meeting is scheduled for 10am WST on 30 November 2026 in Perth. Shareholders will vote on a late-added resolution for an extra 10% Placement capacity under Listing Rule 7.1A. After that, the company's stated milestone is a final investment decision on Watershed in December 2026.

Key Insights

Watershed’s reported feasibility case provides defined inputs, not a guarantee of returns. Tungsten prices, funding terms, construction costs and commercial agreements will remain central ahead of the targeted December investment decision.