Key Highlights
- The Steinert ore sorter has treated 5,412 tonnes since first production on 26 October 2026.
- The sorter product averaged 4.39 g/t gold from development ore averaging 0.86 g/t gold.
- Between 80 and 90 % of the gold in feed was recovered into 16 % of the mass.
- Commissioning is continuing, with the focus on increasing sorter operating hours and optimising settings.
Meeka Metals Limited (ASX:MEK) has reported initial results from commissioning of a new Steinert multi-sensor ore sorter at its Murchison Gold Project in Western Australia. The company said the sorter product averaged 4.39 grams per tonne gold from low-grade development ore averaging 0.86 g/t gold, a fivefold increase in grade. Reject material averaged 0.18 g/t gold. The results follow first production from the sorter on 26 October 2026.
Plant Upgrade and Throughput
The sorter is part of a processing plant upgrade comprising an additional crushing circuit, a wash plant and the sorter installed ahead of the mill. It scans crushed and washed rock in the 16 to 60 millimetre size range and separates high-grade product from low-grade reject. Commissioning feed has been drawn from a stockpile of about 50,000 tonnes of low-grade underground development ore. Between 26 October and 15 November 2026, the sorter treated 5,412 tonnes and produced 882 tonnes of product. Throughput averaged 60 tonnes per hour, and 3,976 tonnes were treated in the week to 15 November. About 16 % of the mass is stockpiled as high-grade product for delivery to the mill.
Gold Recovery and Operating Focus
Over the early shifts, the sorter recovered 80 to 90 % of the gold in feed into 16 % of the mass. The managing director and chief executive, Tim Davidson, said the sorter had taken low-grade material grading less than 1 g/t gold and delivered a product grading more than 4 g/t. The company said the main gain in throughput will come from keeping the sorter fed for more hours each day. Higher-grade feed is expected to support plans to lift gold production, alongside growing underground production from Andy Well and first ore from the Fairway decline at Turnberry in January 2027.
Final Perspective
The results come from the first three weeks of production, and the company says commissioning is continuing. Results reflect commissioning feed rather than a full production run, and the company has not yet provided a longer-term recovery or throughput figure. Further updates on sorter hours and settings will show whether the early recovery and grade results are sustained.