Key Highlights
- Vulcan Energy Resources' quarterly activities report for the three months to 30 September 2026, released on 30 October 2026, shows a company deep in construction.
- Management described drilling and construction at its Lionheart project in Germany as on schedule and within budget, with first production still targeted for 2028.
- The report confirmed funding drawdowns are under way, while identifying technical and scheduling items that remain open.
- For a member of the S&P/ASX 200, Vulcan remains unusual: it has no lithium sales yet, so its story rests on execution.
Vulcan Energy Resources (ASX:VUL) is developing a combined Geothermal Energy and lithium Business in the Upper Rhine Valley brine field, which straddles Germany and France.
Vulcan Energy Resources' quarterly activities report for the three months to 30 September 2026, released on 30 October 2026, shows a company deep in construction. Management described drilling and construction at its Lionheart project in Germany as on schedule and within budget, with first production still targeted for 2028.
The report confirmed funding drawdowns are under way, while identifying technical and scheduling items that remain open. For a member of the S&P/ASX 200, Vulcan remains unusual: it has no lithium sales yet, so its story rests on execution.
What Vulcan does
Vulcan is developing a combined geothermal energy and lithium business in the Upper Rhine Valley brine field, which straddles Germany and France. The concept is to pump hot, lithium-bearing brine from deep wells, use its heat to generate renewable power and heat, extract lithium through adsorption-based direct lithium extraction, and then reinject the brine underground.
The Lionheart project is designed to produce 24,000 tonnes a year of battery-grade lithium hydroxide monohydrate, alongside about 275 gigawatt hours of renewable power and 560 gigawatt hours of heat, over a roughly 30-year life.
Latest developments
During the quarter Vulcan completed its seventh Lionheart well, LSC-3a, a horizontal reinjection well drilled to a measured depth of 3,743 metres. Testing after the quarter indicated injection capacity of about 64 litres per second, against a development assumption of roughly 40.
Work on the Trappelberg well pad advanced, with a drilling rig due to mobilise there in the December quarter. Construction of the first section of the pipeline network is targeted for completion in the third quarter of 2027, with contract awards for later sections expected before the end of 2026.
The geothermal plant and lithium extraction plant are in early construction, and production of adsorbent for the first Fill of the extraction columns has started in Germany. Vulcan also signed a services agreement with licensee EAU Lithium covering Bolivia.
The financial picture
Vulcan's Lionheart funding package totals about 2.2 billion euros of equity, Debt and grants. In the September quarter the company received 53.7 million euros from the first two strategic Equity drawdowns and 10.7 million euros of German government grant payments.
Development spending was 88.8 million euros in the quarter and 256.8 million euros year to date. Vulcan ended September with 129.4 million euros in cash plus 80.0 million euros in term deposits, totalling 209.4 million euros. Further equity instalments are expected until the first debt drawdown, which is targeted for the March quarter of 2027.
The company does not currently pay a dividend.
Risks and uncertainties
The central risk is execution. Lionheart combines deep drilling, a pipeline network, a power plant and chemical plants, and delays or overruns could affect the timetable and conditional funding drawdowns.
Lithium prices are another uncertainty, as project Economics depend on prices when production begins. The report did not disclose offtake terms, noting only that product is being sent to offtake partners for testing.
The Insheim power plant was under maintenance, with power delivery targeted to resume at the end of 2026. Project delivery also depends on completing outstanding technical and scheduling milestones.
Milestones to watch
Near-term items include completion of the Trappelberg pad, rig mobilisation, pipeline contract awards and a Supply contract with ABB, all targeted for the December quarter.
Beyond that, the first debt drawdown in early 2027, completion of the first pipeline section in the third quarter of 2027 and commissioning in 2028 are the key markers. Management has said no Investment decision on the follow-on Project Ludwig will be made until Lionheart is operating successfully.