Highlights
- Quantum Graphite (ASX:QGL) reported that Uley 2 process plant design was approximately 80% complete in September.
- The company continued reviewing its Capital and operating cost estimates against an earlier feasibility study.
- Quantum is developing an Australian flake graphite project alongside proposed Downstream refining and thermal-storage partnerships.
- The September Quarterly Report showed limited cash and reliance on related-party loans and prospective additional funding.
Quantum Graphite (ASX:QGL) holds flake graphite deposits on South Australia’s Eyre Peninsula and is progressing the Uley 2 development concept. Its 2026 updates describe front-end engineering, a cost review and downstream processing opportunities. The main distinction is between progress on technical design and the substantial financing required before construction could proceed.
Uley 2 Engineering and Feasibility Work
Quantum owns the Uley graphite deposits near Port Lincoln, with Uley 2 representing its proposed next mine development phase. The September quarterly report reiterated a Uley 2 ore reserve of approximately 4.0 million tonnes at 11.89% graphitic carbon, based on an estimate dating from 2019. An earlier phase-one study contemplated Capital Expenditure of AUD 152.7 million and production of 100,000 dry tonnes of concentrate annually. On 21 September 2026, Quantum reported front-end engineering and design progress, with process plant design around 80% complete and the capital and operating-cost review approximately 75% complete. The company had not published a revised capital estimate, so earlier study figures should not be assumed to reflect current construction costs.
Graphite Concentrate and Proposed Refining in Oman
Quantum intends to process flake graphite concentrate in South Australia and establish downstream refining capacity at Al Buraimi in Oman. Its refining technology relationship with Sunlands Pure is designed around producing high-purity graphite, while a separate Sunlands Power venture is exploring thermal-energy storage products using Uley material. These are different commercial initiatives with different development and funding requirements. The company has described discussions on an Oman land Lease as well advanced, rather than completed. Further work is needed to clarify engineering, capital costs and the commercial model for refining. Announced technology objectives and proposed products should not be treated as proven commercial output.
Liquidity, Related-Party Loans and FY26 Results
The company’s September-quarter Cash Flow report showed approximately AUD 50,000 in cash at 30 September, following operating outflows of about AUD 1.22 million. Quantum subsequently reported approximately AUD 80,000 in cash at 30 October. Related-party facilities from Pershing Nominees and Chimaera Capital had funded approximately AUD 11.6 million of borrowings; disclosed Loan terms include 11.75% interest and Maturity in December 2027. The company estimated around 1.3 quarters of funding at the reported spending rate and indicated it expected continued Shareholder support or new financing. FY26 statutory accounts recorded a net loss of approximately AUD 4.5 million and highlighted material uncertainty regarding continued operations, while the audit opinion was unmodified.
Remaining Investment and Delivery Requirements
Quantum has not announced fully committed construction financing for the Uley 2 plan. The engineering and cost review may change the expenditure ultimately required, and downstream refining brings additional delivery and commercial dependencies. In November, the company also discussed its views on critical-minerals Supply chains through a parliamentary committee submission, emphasising processing capability and government support. Such policy engagement does not amount to project funding approval. Potential lenders will need to assess costs, product specifications, demand, technical performance and the company’s near-term liquidity. The next meaningful milestones are a completed design and cost update, financing arrangements and clearer development timing. No firm construction decision date was established in the reviewed material.
Key Insights
Uley 2 engineering is progressing, but the current project cost and financing package remain outstanding. Limited cash, borrowing obligations and the proposed Oman refining programme make funding and execution central to the development timetable.