Key Highlights
- Jade Gas Holdings Ltd (ASX:JGH) has completed Mongolia’s first multilateral coal bed methane well at its Red Lake site, ahead of its end-November target.
- The well has a main wellbore and four lateral branches, with a combined 2,642 metres of in-seam drilling, which the company says is about 93% of the horizontal length in the target coal seam.
- A progressive cavity pump is installed, and dewatering of all three wells is expected to start before the end of November 2026.
- Drilling and production results are intended to inform the development drilling program targeted for 2027.
Jade Gas Holdings Ltd (ASX:JGH) has drilled and completed Mongolia’s first multilateral coal bed methane well at Red Lake, within its flagship Mongolian CBM Project. The announcement, dated 19 November 2026, says the well was completed ahead of the end-November target by drilling contractor Yan’an Drilling Wellking Energy Technical Service. The company is now preparing for coordinated dewatering of the new well and its two existing single-lateral wells.
Design and Drilling of the Multilateral Well
The well, identified as RL-001-3b-ML-03, comprises a main wellbore and four lateral branches targeting Seam IIIb, which is the same coal seam intersected by Jade’s two existing horizontal production wells. The contractor reported a combined horizontal drilling length of 2,841.6 metres, of which 2,642 metres lies within the target coal seam. Real-time geosteering guided the trajectories through the seam.
The main wellbore has a slotted liner, while the four laterals are open-hole completions. Jade says the design increases contact with gas-bearing coal from a single wellbore, which could widen the drainage area and affect gas recovery and flow rates. The company has not yet reported production performance from the well.
Dewatering Preparations and Existing Wells
Jade has installed a progressive cavity pump and wellhead motor in the new well and completed trenching for the water and gas pipelines. Workovers and maintenance are under way on the two existing single-lateral wells, HZ01 and HZ02. Dewatering of all three wells is expected to start simultaneously before the end of November 2026, once surface preparation and workovers are complete.
The company says monitoring the three wells together will help it assess reservoir pressure responses and refine dewatering practice. Water production, pressure and gas flow data will guide operational changes, and the gas production capability of the new well will be assessed as dewatering progresses.
Context for the Mongolian Project
Jade describes itself as having moved from explorer to developer after Mongolia’s first Natural Gas reserves were formally approved in June 2026. Its flagship TTCBM Project covers the Production Sharing Agreement area of the Tavantolgoi XXXIII unconventional gas Basin and is operated through a joint venture with the Mongolian Government. The company also holds a joint venture for coal bed methane rights over Mongolia Mining Corporation’s adjacent Baruun Naran coal mine, known as the BNG Project.
Jade says its long-term strategy is to Supply gas to the power and transport sectors, starting in the South Gobi, and it is considering compressed and liquefied natural gas options. The company has not set out Revenue or production targets in the announcement.
Looking Ahead
The coming weeks will show whether dewatering of all three wells begins on schedule and how the new multilateral well performs once production testing is under way. Jade has said its findings will shape the configuration and completion practices for the larger development drilling program it targets for 2027.