Western Gold Resources (ASX:WGR) has entered into a binding Ore Purchase Agreement with Forrestania Resources Limited (ASX:FRS) to process Gold Duke ore at the Edna May processing facility, while also securing a A$7.5 million placement with Forrestania as a cornerstone investor, according to an AGM presentation filed with the exchange in November 2026.

Key Points

  • Binding Ore Purchase Agreement with Forrestania Resources to process up to 1.1 Mt of Gold Duke ore at Edna May over 30 months, with no conditions precedent
  • A$7.5 million placement of 93,750,000 shares at A$0.08 each in two tranches, with Forrestania contributing A$5.5 million as cornerstone investor representing approximately 17.6% of WGR on completion
  • Gold Duke Mineral Resource stands at 277,000 ounces, with a production target of 1.11 Mt at 1.7 g/t for 55,500 recovered ounces
  • Expanded Scoping Study indicates an undiscounted operating surplus of A$72.9 million at A$6,100 per ounce, with pre-mining capital of A$5.35 million and a break-even of A$4,120 per ounce
  • Two new board appointments disclosed: David Geraghty as Non-Executive Chairman and Daniel Cowley-Cooper

Binding Ore Purchase Agreement with Forrestania Resources

Under the binding Ore Purchase Agreement, Forrestania Resources Limited (ASX:FRS) will process Gold Duke ore at the Edna May processing facility. The agreement covers up to 1.1 million tonnes over a 30-month period and carries no conditions precedent. Pricing under the agreement is set by ore grade, recovery and the prevailing gold price, with Western Gold Resources responsible for haulage costs. The company disclosed that its existing Wiluna toll milling agreement remains in place alongside the new Ore Purchase Agreement.

A$7.5 Million Placement and Cornerstone Investment

Western Gold Resources disclosed a A$7.5 million placement comprising 93,750,000 shares at A$0.08 each, to be issued in two tranches, with the second tranche subject to shareholder approval. Forrestania Resources is contributing A$5.5 million as the cornerstone investor, which the company stated represents approximately 17.6% of WGR upon completion of the placement. According to the filing, proceeds are intended to fund site clearing, approximately 12,000 metres of Life of Mine extension drilling, evaluation of processing options and working capital.

Gold Duke Project Resource and Scoping Study Economics

The Gold Duke project in Western Australia's Goldfields region holds a Mineral Resource of 277,000 ounces, with 82% classified as Measured and Indicated. The production target is 1.11 Mt at 1.7 grams per tonne for 55,500 recovered ounces, with pits ranging from 17 metres to 65 metres deep and a stated 93% recovery rate. The Expanded Scoping Study, based on Wiluna toll treatment, reported an undiscounted operating surplus of A$72.9 million at A$6,100 per ounce, pre-mining capital of A$5.35 million, a break-even gold price of A$4,120 per ounce and a 10-month payback period. The company noted that the mine plan and economics are being updated to reflect the Ore Purchase Agreement.