Tesoro Gold Limited (ASX:TSO) has disclosed that multiple indicative, non-binding debt financing proposals have been received for its El Zorro Gold Project in Chile, with the aggregate amount of proposals substantially exceeding the targeted senior debt facility, as the company advances toward a binding financing commitment targeted for Q2 2027.
Key Points
- Multiple indicative, non-binding debt financing proposals received for an aggregate amount substantially exceeding the targeted senior debt facility for El Zorro
- Binding project financing commitment targeted for Q2 CY2027, with lender due diligence currently underway
- Definitive Feasibility Study (DFS) targeted for delivery in Q1 2027, following a delay in confirmatory metallurgical testwork due to damage to drill core samples during transportation
- Environmental Impact Assessment (EIA) submission to Chilean authorities remains on schedule for February 2027
- Santiago Court of Appeals denied all appeals by joint venture partner Wanaco SpA on 10 November 2026, with the court having previously dismissed Wanaco's claims and ordered it to pay costs
El Zorro Project Financing Process
Tesoro is pursuing a funding strategy targeting debt funding for approximately 60% of El Zorro's project development capital, with specialist project finance advisory firm BurnVoir Corporate Finance supporting the process. The competitive funding process, commenced following release of the El Zorro Pre-Feasibility Study in September 2026, attracted interest from international and Latin American commercial banks, government lenders and specialist resource financiers. Several prospective financiers completed site visits to El Zorro in November 2026 as part of their ongoing due diligence. The proposals remain subject to completion of due diligence and each respective lender's credit approval process. Tesoro has also received proposals for an interim funding facility to potentially advance early project works and secure long-lead equipment.
Definitive Feasibility Study Status and Metallurgical Testwork Delay
Final engineering designs have been completed for several major components of the planned El Zorro operation, including the processing plant, waste rock dump, dry stack tailings storage facility, water pipeline and pumping infrastructure, high-voltage power supply infrastructure, accommodation camp, offices, ancillary buildings and access roads. A final programme of confirmatory metallurgical testwork experienced a delay after drill core samples were damaged during transportation to ALS Metallurgical Laboratories in Perth, Western Australia. Tesoro has selected replacement samples from existing metallurgical drill core stored at El Zorro, which have been dispatched to ALS. The DFS is now targeted for delivery in Q1 2027, with the company stating the broader project development timetable, including permitting, is unaffected.
Wanaco Legal Proceedings and EIA Permitting Update
On 10 November 2026, Tesoro received notice from the Santiago Court of Appeals that all appeals filed by its El Zorro joint venture partner Wanaco SpA had been denied. The underlying claims, relating to an alleged abandonment of works under the option and joint venture agreement, had previously been dismissed by the 29th Civil Court of Santiago on 31 August 2024, with Wanaco ordered to pay costs. Wanaco had exercised its right to appeal that judgement, as announced on 28 October 2025. Separately, Tesoro disclosed that final documentation is being compiled for submission of the project's Environmental Impact Assessment to the relevant Chilean authority, with submission targeted for February 2027.