Strike Energy (ASX:STX) has announced the successful energisation of its 85 MW South Erregulla Power Plant (SEPP) on 20 November 2026, completing construction and connecting the facility to Western Australia's South West Interconnected System (SWIS), with Australian Energy Market Operator hold-point testing now underway.
Key Points
- The South Erregulla Power Plant was successfully energised and connected to the SWIS on 20 November 2026, in conjunction with Western Power.
- A total of $187 million (excluding capitalised interest) has been invested in the project, comprising $153 million for the power plant, $32 million for grid connection infrastructure and $2 million for operational readiness.
- AEMO hold-point testing is expected to take approximately six to eight weeks, with commercial operations targeted for late January 2027.
- Capacity Credit revenues have been secured through Capacity Year 2029, with illustrative capacity revenue of approximately $39 million per year and additional electricity sales revenue of approximately $36–$42 million per year.
- Ragan Stonier has been appointed Chief Operating Officer, bringing more than 30 years of experience across the energy sector and power station operations.
Energisation and AEMO Hold-Point Testing Process
Energisation of the South Erregulla Power Plant was completed on 20 November 2026 in conjunction with Western Power, enabling the commencement of hold-point testing activities with AEMO. During testing, the facility's output will progressively increase from 10 MW to full nameplate capacity of 85 MW in stages. At each hold-point, testing is conducted to confirm the facility responds correctly to changes in grid voltage and frequency and matches technical models. Results are reviewed by AEMO and Western Power before the station proceeds to the next stage. During commissioning, electricity dispatched into the grid earns revenue at prevailing Real Time Market spot prices in the Wholesale Energy Market.
Project Composition and Capital Investment
The South Erregulla Power Plant has been developed on Strike's 3,500-hectare freehold land and comprises 20 Jenbacher gas-reciprocating engines, 16.5 kilometres of 132 kV transmission lines and three new switchyards connecting the facility to the SWIS. The project's total capital investment of $187 million compares with the Final Investment Decision cost of $137 million sanctioned in November 2024. The $48 million increase, excluding operational readiness, is primarily attributable to expanded scope to incorporate Western Power-designed transmission infrastructure, additional upstream and well workover activity, engineering costs, general inflationary effects and delayed project completion.
Capacity Credits and Revenue Profile for Capacity Year 2029
The South Erregulla Power Plant has secured Capacity Credits through Western Australia's Reserve Capacity Mechanism. For Capacity Year 2029, covering 1 October to 30 September, the filing illustratively discloses capacity revenue of approximately $39 million per year and additional electricity sales revenue of approximately $36–$42 million per year. The filing also notes significant operating margin benefits from direct access to Strike-owned gas reserves, with low-cost gas supply sourced from the 100% Strike-owned South Erregulla field. Capacity Credit revenues are described as a contracted revenue stream independent of electricity sales.