RTG Mining Inc. (ASX:RTG) has confirmed it and Philippine partner TVI Resource Development (Phils.) Inc. remain committed to a Final Investment Decision on the Mabilo Copper and Gold Project targeted early in the fourth quarter of 2026, with Stage 1 fully funded through a binding finance and offtake term sheet with Glencore International AG.
Key Points
- RTG Mining Inc. (ASX:RTG, TSX:RTG) released its quarterly activities report for the period ended 30 June 2026
- Final Investment Decision on the Mabilo Project targeted early Q4 2026, with operational start-up expected approximately eight months later
- Stage 1 DSO draws on 0.104Mt of supergene chalcocite at an average reserve grade of 20.7% Cu, expected to produce about 25,200 tonnes of copper and 52,900 ounces of gold
- Investors may be watching for the FID, permitting completion, and drilling results at Mabilo and Chanach
Mabilo Stage 1 DSO Fully Funded via Glencore Facility of up to US$30M
The company said Mt. Labo, in which RTG holds a 40% interest, executed a binding finance and offtake term sheet with Glencore to fund 100% of Stage 1 planned capital expenditure. The secured facility provides up to US$30M across three tranches: Tranche A (US$3.5M) for land acquisition, Tranche B (US$21.5M) for the balance of development and working capital, and Tranche C (US$5.0M) for additional working capital subject to consent. RTG also holds a 2% net smelter royalty and a loan to Mt. Labo of approximately US$27 million.
Stage 1 Grades of 20.7% Cu Underpin Early Cashflow
RTG stated the Mabilo Stage 1 development is a direct shipping ore (DSO) operation requiring no plant construction, with development primarily comprising a pre-strip program. The primary ore source is 0.104Mt of supergene chalcocite material at an average reserve grade of 20.7% Cu, expected to produce approximately 25,200 tonnes of copper plus an additional 52,900 ounces of gold from other products. The company said the project potentially commences operations in the first half of 2027, and noted copper continues to trade above US$6.00/lb.
Chanach Gold and Copper Project Prepares for New Field Season
RTG holds a 90% majority stake in the Chanach Gold and Copper Project in the Kyrgyz Republic. The company said no field work was undertaken during the quarter due to weather restrictions, but preparations for the new field season were conducted, including contracting a drilling and earthworks company and a laboratory for sample analysis. Mobilisation to site started early July. Infill drilling of the epithermal gold vein system and some high-grade skarns was planned, targeting an upgrade of resource status, with drilling expected late July to early August.
What RTG's A$8.3M Cash Position Means for Shareholders
The company reported cash and liquid assets of A$8.3 million as at 30 June 2026. With Stage 1 capital expenditure at Mabilo funded 100% through the Glencore facility, RTG stated its loans to Mt. Labo, currently around US$27 million (A$39.1 million), are to be repaid early out of Stage 1 DSO proceeds, subject to customary liquidity and external debt requirements. The company said key remaining tasks before a development commitment include finalising conversion and permitting for coconut tree felling.