PhosCo (ASX:PHO) has released an updated Scoping Study on its Gasaat Phosphate Project in Tunisia, reporting an after-tax net present value of US$732 million at a 10% discount rate and an after-tax internal rate of return of 52%, with a projected payback period of 20 months from the commencement of commercial production.

Key Points

  • After-tax NPV₁₀ of US$732 million and IRR of 52%, with a 20-month payback from commercial production on a 100% project basis
  • Development capital of US$199 million to deliver 1.4 million tonnes per annum of phosphate concentrate
  • Total project revenue of US$10 billion at an average price of US$152 per tonne of phosphate concentrate
  • 49-year mine life with a production target of 134 million tonnes at 19.9% P₂O₅ from a Global Mineral Resource of 166.6 million tonnes at 20.6% P₂O₅
  • Estimated funding requirement of approximately US$220 million, with EBRD providing a €1 million grant toward the Scoping Study update and an option for a further A$7.5 million equity investment toward feasibility work

Gasaat Phosphate Project Financial Parameters

The 2026 Scoping Study Update discloses average annual net cashflow of US$106 million for the first ten years of production. Total project revenue is stated at US$10 billion, calculated at an average price of US$152 per tonne of phosphate concentrate. The study is completed to an accuracy level of plus or minus 35%, consistent with scoping study standards. The company disclosed that funding of approximately US$220 million will likely be required and that potential financing sources include development banks, international banks, resource credit funds, offtake agreements, joint venture partners, and partial asset sales. The European Bank for Reconstruction and Development has expressed interest in project funding.

Metallurgical Breakthrough and Two-Product Concentrate Output

The updated study incorporates a metallurgical advancement enabling a simplified, single-stage flotation flowsheet, which the company said reduces both capital and operating costs. The process is designed to produce two product streams: a premium grade phosphate concentrate of approximately 33% P₂O₅, representing 30% of sales at US$180 per tonne, and a standard grade phosphate concentrate of approximately 30% P₂O₅, representing 70% of sales at US$140 per tonne. The planned processing facility is sized at a nameplate feed tonnage of 2.8 million tonnes per annum, targeting output of 1.4 million tonnes per annum of concentrate at greater than 30% P₂O₅ and less than 1% MgO.

Mine Life, Strip Ratios, and Government Backing

The Gasaat project is planned as an open-pit operation with a 49-year mine life. The first four years of production are scheduled from the KM prospect, which carries a strip ratio of 0.5:1, before transitioning to the SAB and KEL deposits for approximately 20 years. The strip ratio for the first ten years averages 2.5:1, scheduled from Measured (55%), Indicated (33%), and Inferred (12%) Mineral Resources. The Tunisian Government granted the Gasaat project to PhosCo on a 100% basis in March 2025, and a memorandum of understanding was signed with the Tunisian Ministry of Industry, Mines and Energy and the EBRD to develop Tunisia's Northern Phosphate basin hub.