Northern Minerals (ASX:NTU) has released its annual report for the financial year ended 30 June 2026, disclosing key metrics from the Definitive Feasibility Study (DFS) for its Browns Range Heavy Rare Earths Project, including pre-production capital of A$592 million, an estimated NPV8 of A$705 million, and an internal rate of return of 21% under the Divergence Case.
Key Points
- Browns Range DFS indicates pre-production capital of A$592 million and an NPV8 of A$705 million at a 21% IRR under the Divergence Case
- Mineral Resources of 7.5 Mt at 0.96% TREO and Ore Reserve of 5.2 Mt at 0.88% TREO, with an 11-year mine life at approximately 560 ktpa
- First concentrate production is targeted for late 2028, subject to project funding; Final Investment Decision remains dependent on funding arrangements
- Some satisfaction dates for conditions precedent under the Supply Agreement with Iluka have passed, which may entitle Iluka to terminate the agreement; parties are in discussions
Browns Range DFS Project Metrics
According to the filing, the Browns Range Heavy Rare Earths Project holds Mineral Resources of 7.5 Mt at 0.96% Total Rare Earth Oxide (TREO) and an Ore Reserve of 5.2 Mt at 0.88% TREO. The project is designed for an 11-year mine life operating at approximately 560 ktpa, producing 17.5 ktpa of concentrate with up to 4,350 tpa TREO in concentrate, averaging 25% TREO concentrate. The project incorporates open pit mining with a single-stage cutback and underground mining using longitudinal sub-level cave methodology, with a conventional flowsheet involving grinding, magnetic separation, and flotation. The DFS was originally announced on 15 September 2025.
Pathway to Production and Final Investment Decision
The filing states that Browns Range is progressing through financing, Final Investment Decision (FID), and construction towards first production targeted for Q4 2028 or Q1 2029, subject to project funding. Front End Engineering and Design (FEED) has commenced, and key approvals are described as in place. The company disclosed that funding arrangements and associated negotiations are continuing to progress as it advances towards FID. The filing confirms that all material assumptions underpinning the Production Target and Forecast Financial Information from the 15 September 2025 DFS announcement continue to apply and have not materially changed.
Supply Agreement Risk and Basket Value Composition
The filing disclosed that some satisfaction dates for certain conditions precedent under the Supply Agreement with Iluka have passed as at the date of the annual report, noting this may entitle Iluka to terminate the Supply Agreement. The parties are described as being in discussions to facilitate satisfaction of conditions or agree suitable extensions. Separately, the filing states that dysprosium, terbium, and yttrium contribute approximately 78% of the Browns Range basket value, with dysprosium accounting for 48%, terbium 22%, and yttrium 8%, based on average individual rare earth oxide prices in 2024.