Minerals 260 Limited (ASX:MI6) has ordered key long-lead items for its 100%-owned Bullabulling Gold Project, with CITIC Heavy Industries selected to supply SAG and ball mills and Metso Corporation to supply the primary crusher, following a competitive tender process and on-site inspections of manufacturing facilities in China.
Key Points
- CITIC Heavy Industries will supply SAG and ball mills, including access to their Intelligent Grinding Expert System; Metso Corporation will supply the primary crusher.
- Village construction is over 50% complete and on schedule to be operational in Q1 CY2027.
- 24 water bores have been installed, with test pumping and modelling underway; water exploration expanded to support the 7.5Mtpa production goal.
- A 70,000m grade control drilling program has commenced, designed to de-risk the initial nine months of production at a drill spacing of 10m x 10m.
- The Definitive Feasibility Study (DFS) remains on track for completion in Q1 CY2027, with a Final Investment Decision (FID) also targeted for Q1 CY2027.
Long-Lead Equipment Orders for Bullabulling Gold Project
The long-lead items were ordered following a competitive tender process that included on-site inspections of manufacturing facilities in China. The agreement with CITIC Heavy Industries includes access to their Intelligent Grinding Expert System, described in the filing as an integrated control platform providing real-time mill condition monitoring, online particle size measurement, and fault diagnostics to support stable mill operation and condition-based maintenance. The Bullabulling Gold Project is located 65km west of Kalgoorlie in Western Australia and hosts a JORC 2012 Mineral Resource Estimate of 190Mt at 1.0g/t Au for 6.2Moz of gold, on granted mining leases.
Village Construction and Water Infrastructure Progress
Village construction at the Bullabulling site is more than 50% complete and remains on schedule to be operational in Q1 CY2027, ahead of major construction activities following a planned FID in the same quarter. Water infrastructure installation is also progressing, with 24 bores installed and test pumping and modelling underway. The filing states that water exploration has been expanded to support the company's 7.5Mtpa production goal. Remaining approvals for the project are under assessment through the Western Australian State approvals pathway and are described as on track to support FID.
Grade Control Drilling and DFS Timeline
Final analysis of an initial 26,000m grade control program has been completed, with the grade control model reconciling to within plus 1% of contained gold within the 6.2Moz Mineral Resource Estimate. A 70,000m grade control drilling program has commenced, using a drill spacing of 10m x 10m consistent with the initial program, and is designed to further de-risk the initial nine months of production. The DFS remains on track for completion in Q1 CY2027 and will include the pathway to achieve the company's production goal of 7.5Mtpa. Managing Director Luke McFadyen noted the project is fully funded through to first production.