MGX Resources Limited (ASX:MGX) has released its CEO presentation to shareholders at the company's 2026 Annual General Meeting, outlining the Central Tanami Project Joint Venture, an agreed sale of Koolan Island iron ore mine for at least $20 million, and the company's stated aim to become a new Australian gold producer within three years.
Key Points
- MGX holds a 50% interest in the Central Tanami Project Joint Venture with Tanami Gold NL (ASX:TAM), which carries a JORC 2012 Mineral Resource of 2.8 Moz gold (31 Mt at 2.8 g/t Au).
- The company has agreed to sell Koolan Island iron ore mine for at least $20 million, with approximately $30 million in rehabilitation obligations to be transferred.
- Cash and investments stood at A$409 million as at 30 September 2026, with no bank borrowings.
- Underground exploration decline construction at the Groundrush deposit is underway, comprising 3.5km of lateral development to 350 metres below surface over 14 months.
Central Tanami Project Joint Venture Details
The Central Tanami Project Joint Venture (CTPJV) is a 50/50 arrangement between MGX and Tanami Gold NL. The project holds a JORC 2012 Mineral Resource of 2.8 Moz gold (31 Mt at 2.8 g/t Au), including 1.2 Moz (11 Mt at 3.3 g/t Au) in the Groundrush deposit. The project features more than 50 known gold deposits and historical production of 2 Moz. Initial development focus is on the Groundrush, Jims and Ripcord free-milling deposits, which together contain more than 1.5 Moz Au. Existing site infrastructure includes mine haul roads, a water borefield, an accommodation camp and a 1.4km gravel airstrip, with initial refurbishment activities underway.
Groundrush Underground Exploration Decline Construction
The Groundrush deposit is located on a granted mining lease, 41km north of the existing CTPJV plant site via a sealed haul road. Previous open pit gold production by Newmont totalled more than 0.6 Moz at an average grade of 4 g/t Au between 2001 and 2005. Macmahon Underground was appointed mining contractor in August, and both the Central and ventilation portals have been constructed, with decline construction now underway. The underground decline will comprise 3.5km of lateral development to 350 metres below surface over 14 months. Infill drilling of 33,000 metres from underground headings will target conversion of over 400,000 oz Au of Inferred Resources to Indicated status for mine planning purposes.
Jims Gold Deposit Resource Definition and Corporate Overview
The Jims Gold Deposit holds a current Mineral Resource estimate of 220,000 oz (2.6 Mt at 2.7 g/t Au) and is located on a granted mining lease, 23km south of the existing CTPJV plant site. The resource remains open down plunge to the north and along strike over an 870-metre footprint. Resource definition RC drilling of 16,000 metres was completed in September, with a follow-on diamond drilling program described as almost complete. Results are being collated for release in the near term. At the corporate level, the company reported 1,180 million shares on issue and a market capitalisation of A$354 million at $0.30 per share, with no bank borrowings disclosed.