Iondrive Limited (ASX:ION) has released an updated corporate presentation dated November 2026, disclosing the commissioning status of its five-tonne trial, economics from a pre-FEED screening-level study, and the status of commercial negotiations for its IONSolv rare earth recovery platform targeting end-of-life NdFeB magnets in the United States.
Key Points
- The five-tonne trial is in commissioning, with one tonne of feedstock on site and four tonnes in transit, targeting approximately 1.4 tonnes of mixed rare earth oxide for customer qualification.
- A pre-FEED screening-level study disclosed a US$243 million post-tax NPV and US$62.1 million EBITDA per year from one modelled module, on US$11.9 million of plant capital; working capital is additional.
- Seven prospective feedstock and offtake counterparties are engaged; no supply or offtake has been contracted and no funding has been awarded.
- An Oklahoma site lease is nearing finalisation, conditional on the five-tonne trial outcome and due diligence.
Five-Tonne Trial Commissioning and Technology Results
According to the filing, the five-tonne trial is being commissioned with one tonne of end-of-life NdFeB magnet feedstock on site and four tonnes in transit. The trial is described as the first integrated test of the estimated overall flowsheet recoveries of 89.3% neodymium, 88.5% praseodymium and 88.8% dysprosium. Independent leach tests previously disclosed returned 96.5% neodymium, 96.5% praseodymium and 93.5% dysprosium with 99.9% iron rejection. The company stated that FEED follows technical validation, subject to board approval. The trial is noted as not yet at commercial scale.
Pre-FEED Screening-Level Study Economics
The corporate presentation disclosed a pre-FEED screening-level study for one modelled module showing a US$243 million post-tax NPV and US$62.1 million EBITDA per year, on plant capital of US$11.9 million, with working capital described as additional. The filing explicitly states these modelled study outputs are not forecasts and that the NPV is not a valuation of the company and is not multiplied across modules. Module 1 is based on 2,402 tonnes per annum of feed, described as approximately one fifth of a retiring pool cited at approximately 13,000 tonnes currently. First production planning assumption for Module 1 is disclosed as 2028.
Commercial Position and Oklahoma Site Lease
The filing states seven prospective feedstock and offtake counterparties are engaged. No supply or offtake agreements have been contracted and no funding has been awarded. An Oklahoma site lease is described as nearing finalisation, conditional on the five-tonne trial outcome and due diligence. The company disclosed a modular growth pathway of up to five modules in the medium term against a projected pool of approximately 29,000 tonnes of end-of-life magnets and swarf by 2033, and up to ten modules by 2050 against a projected pool of approximately 49,000 tonnes. Feed supply, qualification, site and funding are cited as the factors determining pace.