FBR Limited (ASX:FBR) has completed Factory Acceptance Testing of its first Mantis™ welding robot, with independent non-destructive testing by InSpec NDT Pty Ltd confirming full compliance with AWS D1.1/D1.1M:2025 structural welding code requirements, rendering the purchase order unconditional.

Key Points

  • Factory Acceptance Testing completed on the first Mantis™ unit, with the purchase order now unconditional following FAT satisfaction.
  • InSpec NDT Pty Ltd independently confirmed welds met visual, surface, volumetric and magnetic particle inspection criteria of AWS D1.1/D1.1M:2025.
  • Industrial Robotics LLC paid a US$198,000 deposit to secure the first unit; the sales contract has been varied to keep the machine in Perth until January 2027 for a paid pilot program.
  • Demonstrations with Tier 1 mining, shipbuilding, and heavy fabrication groups are planned for the current quarter.
  • A second Mantis™ unit is currently being built.

Factory Acceptance Testing and NDT Certification Outcome

According to the filing dated 8 October 2026, Mantis™ successfully satisfied all FAT parameters, demonstrating automated twin wire welding, rapid travel speeds, and consistent weld deposition, while validating its 8-metre reach and integrated Dynamic Stabilisation Technology® motion compensation. Accredited inspection agency InSpec NDT Pty Ltd conducted non-destructive testing across the test weldments and confirmed that the welds fully satisfied the acceptance criteria of AWS D1.1/D1.1M:2025, validating Mantis™ as producing code-compliant welds suitable for critical structural steel applications.

Sales Contract Variation and Perth Pilot Program Terms

FBR disclosed that it has varied its sales contract for the first Mantis™ unit, previously with State Machinery & Equipment Sales, so that the contract is now held by Industrial Robotics LLC, which was founded by the owner of State Machinery. Industrial Robotics LLC was appointed as non-exclusive distributor of Mantis™ in the United States and Canada in July 2026. Under the varied contract, FBR will receive a deposit of $198,000, and the first unit will remain in Perth, Western Australia for the remainder of calendar year 2026 to undertake a paid pilot program and conduct demonstrations before shipping to State Machinery's Mississippi River facility.

Pilot Program Operations and Second Unit Construction

The filing states that several large industrial companies have provided test piece details to FBR's workshop to undergo trial welding on real-world geometries. FBR noted that immediate shipping would induce approximately eight weeks of operational delay during ocean freight and US import processing. Industrial Robotics LLC will bring prospective US clients to Perth to witness Mantis™ in operation during the pilot program. FBR has planned demonstrations with Tier 1 mining, shipbuilding, and heavy fabrication groups during the current quarter. The company also disclosed that the second Mantis™ unit is currently being built.