CuFe Ltd (ASX:CUF) has disclosed that its integrated Orlando and Gecko Scoping Study and the Tennant Creek Copper Alliance plant engineering and cost estimate study are both approaching finalisation, with results from both expected before the end of 2026, as the company progresses multiple workstreams at its Tennant Creek Project in the Northern Territory.
Key Points
- Integrated Orlando and Gecko Scoping Study has all technical workstreams finalised, with financial modelling well advanced and results expected before end of 2026.
- Tennant Creek Copper Alliance (TCCA) AAEC class 4 engineering capex and opex cost estimate study has all technical workstreams complete, with final report collation well advanced.
- RC drilling is ongoing across Orlando infill and extension targets and the Gecko trend, with first assay results expected in December 2026.
- An updated Orlando Mineral Resource Estimate based on a revised geological model is targeted for release in early 2027.
- A helicopter Mobile MagnetoTellurics (MT) survey is underway to identify subsurface resistivity to depths of 1km to assist in defining 2027 drill targets.
Development Studies Status at Tennant Creek
According to the filing, the integrated Orlando and Gecko Scoping Study represents the first consolidated assessment of full project economics, expanding on previously completed Orlando Scoping Studies through the addition of Gecko following a detailed mine planning and costing exercise. All technical workstreams have been completed, with finalisation of the financial model and collation of the final report described as well advanced. The TCCA study, jointly funded by the Tennant Creek Alliance Partners and the Federal and Northern Territory governments, will deliver a class 4 level engineering capex and opex estimate for a proposed multi-user processing plant in the Tennant Creek region. All technical workstreams for that study have also been completed.
Exploration Drilling and Geophysical Data Acquisition
RC drilling has commenced with infill and extension targets at Orlando and is currently advancing at exploration targets along the Gecko trend. The first batch of samples has been submitted to a laboratory for processing, with results expected in December 2026. Diamond drilling has been delayed due to slippage in the arrival of the original rig, with an alternate rig procured and due to mobilise as of the filing date. The planned diamond drilling program will provide drill core for metallurgical, geotechnical and waste characterisation studies. A helicopter MT survey is concurrently underway, acquiring data to identify subsurface resistivity to depths of one kilometre.
Orlando Resource Re-Interpretation and Waste Landform Opportunity
The company disclosed that internal geological remodelling is underway at Orlando, targeting greater continuity in the ore body through updated geological model and ore wireframe interpretations. This work is to be sent to a third-party consultant to estimate an updated JORC resource for publication in early 2027, after which the methodology will be applied to the Gecko resource. The filing also states the company is investigating the recovery of ore from historical waste landforms at Gecko and Orlando, where high cut-off grades were applied by previous operators. The company is working with environmental consultants to prepare a request to drill or trench the waste landforms to assess the quantum and grades of available material.